Permit: TD-DEV-0524-00155
Permit Details
Apply Date:
05/22/2024
Applicant:
Blake Junak
Description:
New commercial building for Valvoline gas station
Permit Reviews
Permit Number - TD-DEV-0524-00155
Permit Status: Complete
Permit Description: New commercial building for Valvoline gas station
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/11/2026 | AS-BUILT v.1 | 02/18/2026 | REQUIRES RESUBMIT |
| 02/19/2026 | AS-BUILT v.2 | 02/23/2026 | APPROVED |
| 08/27/2024 | DEVELOPMENT PACKAGE NEW v.3 | 08/29/2024 | APPROVED |
| 05/24/2024 | DEVELOPMENT PACKAGE NEW v.1 | 07/11/2024 | REQUIRES RESUBMIT |
| 07/24/2024 | DEVELOPMENT PACKAGE NEW v.2 | 08/23/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TD-DEV-0524-00155
Permit Status: Complete
Permit Description: New commercial building for Valvoline gas station
| Date | Description | Comments |
|---|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0524-00155
Permite Description: New commercial building for Valvoline gas station
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/10/2025 | NPPO Monitoring | N/A | Partial Pass | Contractor that needs to replace all the dead trees in the nursery area |
| 11/10/2025 | N/A | Not Ready | contractor has not started the grading on the drive-through or the parking area | |
| 12/09/2025 | LAND Landscape Appearance & Function Final | N/A | Not Ready | |
| 12/02/2025 | N/A | Partial Pass | Contractor needs to install all the sidewalks covers from the downspout of the roof | |
| 05/27/2026 | ENGR Engineering Final | N/A | Partial Pass | Fix handicap parking striping so it matches detail on page 6. It is .5' short. (And sign- see signage inspection notes) Remove current crosswalk between 6" curb bullnoses between building and Lightpost bullnose. Repaint 4' access aisle so it follows As-built plans ADA route dashed line from where sidewalk has 0" vertical separation at east side of transformer bullnose south around bull nose and west to north end of Refuse Enclosure apron. Fix scupper DG grade where it meets invert of scupper at SE building corner bullnose. They should be the same so water drains correctly to basin. If there is no long term bicycle parking provided outside building than there needs to be a bike hook provided inside for long term storage for employees. |
| 12/05/2025 | COT - ENGR - Signage Final | N/A | Not Ready | ADA parking sign missing |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0524-00155
Permit Description: New commercial building for Valvoline gas station
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/03/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | NPPO all needs to be retagged, completed to,early and most tags are missing, no NPPO nursery area noted on plan. NPPO inspection will be completed after pip plants are tagged and nursery location decided. | |
| 04/15/2025 | NPPO Pre-Construction | Passed | Off-site nursery location approved for TOS tree #8. This is the only plant being preserved. No on-site nursery necessary. Plant will be brought back when ready for final location. | |
| 12/05/2025 | For trash and recycling enclosures | Passed | ||
| 12/09/2025 | Passed | |||
| 12/09/2025 | NPPO Final | Passed | ||
| 05/22/2026 | Consultation SITE | Passed | Discussed outstanding inspections on Development package and requirements for close out of com and dev permits | |
| 05/27/2026 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
| 05/27/2026 | LAND Landscape Appearance & Function Final | Passed | ||
| 05/27/2026 | SITE - Zoning Final | Passed | ||
| 05/27/2026 | ENGR Paving | Passed | ||
| 05/27/2026 | Passed | |||
| 06/01/2026 | ENGR Engineering Final | Passed | ||
| 06/01/2026 | COT - ENGR - Signage Final | Passed |