Permit: TD-DEV-0423-00224
Permit Details
Apply Date:
04/26/2023
Applicant:
Scott Feltheim
Description:
*Revision #2 started 12/14/23* Construction of new athletic fields, basketball courts and associated parking
Permit Reviews
Permit Number - TD-DEV-0423-00224
Permit Status: Issued
Permit Description: *Revision #2 started 12/14/23* Construction of new athletic fields, basketball courts and associated parking
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/09/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 11/15/2023 | APPROVED |
09/29/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 11/07/2023 | REQUIRES RESUBMIT |
12/14/2023 | DEVELOPMENT PACKAGE NEW v.1 | 01/23/2024 | REQUIRES RESUBMIT |
04/27/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 06/21/2023 | REQUIRES RESUBMIT |
08/17/2023 | DEVELOPMENT PACKAGE NEW v.2 | 08/23/2023 | APPROVED |
06/26/2023 | DEVELOPMENT PACKAGE NEW v.1 | 08/07/2023 | REQUIRES RESUBMIT |
01/31/2024 | DEVELOPMENT PACKAGE NEW v.2 | 02/02/2024 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0423-00224
Permite Description: *Revision #2 started 12/14/23* Construction of new athletic fields, basketball courts and associated parking
Total Outstanding Inspections - 10
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/29/2024 | COT - ENGR - Site - Assurance Release | N/A | Partial Pass | 50% |
01/31/2024 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | |
01/29/2024 | ENGR - Drainage Structures | N/A | Not Ready | |
02/06/2024 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | 20 foot drain structure good to pour. |
09/26/2024 | ENGR Grading Final | N/A | Not Ready | Looked over this site for the upper parking lot located at the northeast portion of this site. The contractor is working on placing and grading the ABC today and will start paving the parking lot Friday and finish it next week.a question came up about the roadway width being less than 24 feet wide of open space. I have advised Jason the Engineer of Record to contact Stephen Blood for his determination and Approval As Inspectors we will always consider traffic lanes to be 12 feet wide, anything less requires the direction to be a one way P.A.A.L. if there is not 24 foot wide roadway. |
02/05/2024 | COT - ENGR - Stormwater | N/A | Canceled | rescheduled for 2/6 |
10/02/2024 | PDSD Site/Engineering Division - Landscaping | N/A | Partial Pass | contractor has not completed landscaping as of yet. Good for TC. Of.O |
10/02/2024 | PDSD Site/Engineering Division - NPPO | N/A | Partial Pass | Contractor has not completed all the landscaping as of yet |
10/02/2024 | SITE | N/A | Partial Pass | contractor has not completed the water harvesting in the parking lot good fort.c of o |
11/21/2024 | Consultation SITE | N/A | Partial Pass | Contractors go to grout the sidewalk area from the parking lot of the school leading to the football field. They’re good to grout and they’re also good to pour the sidewalk in that area. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0423-00224
Permit Description: *Revision #2 started 12/14/23* Construction of new athletic fields, basketball courts and associated parking
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/29/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
01/29/2024 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed | ||
01/29/2024 | SITE - Zoning Compliance | Passed | ||
02/01/2024 | ENGR - Drainage Structures | Passed | basin drains 1& 2 (concrete) and stormwater pipe between | |
02/14/2024 | SITE - SWPPP Correction Notice | Passed | wattles along south and west fence line | |
09/16/2024 | For trash and recycling enclosures | Passed | ||
10/02/2024 | NPPO Pre-Construction | Passed | ||
10/02/2024 | COT - ENGR - Stormwater | Passed |