Permit: TD-DEV-0224-00047
Permit Details
Status:
Issued
Type:
Development Package
Address:
4401 S TUCSON ESTATES PW
Address NEW:
4401 S TUCSON ESTATES PW
Apply Date:
02/14/2024
Applicant:
Architecture & Engineering City of Tucson
Description:
Restricted access - Revision 1 - City of Tucson Water Department The new City of Tucson Hayden Udall Warehouse will provide: • New organized and convenient storage spaces. • New offices, workspaces, and support spaces for Tucson Water staff. Note: All Landscape and Native Plant Preservation Plan by COT
Permit Reviews
Permit Number - TD-DEV-0224-00047
Permit Status: Issued
Permit Description: Restricted access - Revision 1 - City of Tucson
Water Department
The new City of Tucson Hayden Udall Warehouse will provide:
• New organized and convenient storage spaces.
• New offices, workspaces, and support spaces for Tucson Water staff.
Note: All Landscape and Native Plant Preservation Plan by COT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/12/2024 | DEVELOPMENT PACKAGE NEW v.1 | 03/19/2024 | REQUIRES RESUBMIT |
| 06/25/2024 | DEVELOPMENT PACKAGE NEW v.3 | 07/03/2024 | APPROVED |
| 08/12/2024 | DEVELOPMENT PACKAGE NEW v.1 | 08/29/2024 | APPROVED |
| 05/13/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 06/10/2025 | APPROVED |
| 03/20/2024 | DEVELOPMENT PACKAGE NEW v.2 | 04/12/2024 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0224-00047
Permite Description: Restricted access - Revision 1 - City of Tucson
Water Department
The new City of Tucson Hayden Udall Warehouse will provide:
• New organized and convenient storage spaces.
• New offices, workspaces, and support spaces for Tucson Water staff.
Note: All Landscape and Native Plant Preservation Plan by COT
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/16/2025 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 07/29/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No issues noticed at this time |
| 12/03/2025 | LAND Landscape Appearance & Function Final | N/A | Partial Pass | 2 saguaros are not yet transplanted and two trees are dead, correct these issues to finalized the Landscape. |
| 12/03/2025 | ENGR Engineering Final | N/A | Partial Pass | 12/3/25 - Site is complete with the exception of installation of EV chargers and minor landscaping issues. Recall for final once complete. Okay for TCO level 4. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0224-00047
Permit Description: Restricted access - Revision 1 - City of Tucson
Water Department
The new City of Tucson Hayden Udall Warehouse will provide:
• New organized and convenient storage spaces.
• New offices, workspaces, and support spaces for Tucson Water staff.
Note: All Landscape and Native Plant Preservation Plan by COT
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2024 | NPPO Pre-Construction | Passed | NPPO inspection done after job started, no nursery needed here. Pre Con was done at the same time as it again was not completed as it should have been . | |
| 01/16/2025 | COT - SITE - Zoning Intermediate | Passed | ||
| 01/16/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
| 01/16/2025 | Verify required native plant protection, relocation, removal is completed prior to activity on job site | Passed | ||
| 10/21/2025 | Passed | 10/21/25 - All sidewalks and flat work is complete in accordance with approved plans. Finish conditions are within acceptable tolerances. Slopes and cross-slopes are correct and in compliance with ADA standards. | ||
| 10/21/2025 | ENGR Paving | Passed | Paving is complete in accordance with approved plans. Finish condition is good. | |
| 10/21/2025 | ENGR Grading Final | Passed | All site grading is complete, finish conditions are functional and in accordance with approved plans. | |
| 12/02/2025 | SITE | Passed | Water harvesting areas are complete and in accordance with approved plans. | |
| 12/03/2025 | COT - ENGR - Signage Final | Passed | All signs are installed in accordance with approved plans. |