Permit: TD-DEV-0123-00124
Permit Details
Apply Date:
01/31/2023
Applicant:
Peter Salonga
Description:
Expansion of existing tile and granite manufacturing facility
Permit Reviews
Permit Number - TD-DEV-0123-00124
Permit Status: Issued
Permit Description: Expansion of existing tile and granite manufacturing facility
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/23/2023 | DEVELOPMENT PACKAGE NEW v.1 | 06/23/2023 | REQUIRES RESUBMIT |
06/23/2023 | DEVELOPMENT PACKAGE NEW v.2 | 06/23/2023 | REQUIRES RESUBMIT |
02/02/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 02/09/2023 | REQUIRES RESUBMIT |
03/14/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 04/17/2023 | REQUIRES RESUBMIT |
05/23/2023 | DEVELOPMENT PACKAGE REVIEW v.3 | 06/16/2023 | REQUIRES RESUBMIT |
06/23/2023 | DEVELOPMENT PACKAGE NEW v.3 | 06/26/2023 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0123-00124
Permite Description: Expansion of existing tile and granite manufacturing facility
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/14/2023 | SITE - Zoning Violation | N/A | Not Applicable | |
05/09/2024 | ENGR - Drainage Structures | N/A | Not Ready | The contractor is working on forming curbs along the west side of the property in the south side of the property. I also have looked at the trash and closure footer. Additional bars have been added in a couple of bars have been missed. They will add the additional bars, and then we’ll start working on constructing the walls for the trash enclosure. |
06/21/2024 | SITE | N/A | Partial Pass | Verts & Bond Beam in place. Ready to grout 2nd lift. |
For trash and recycling enclosures | N/A | Requested | ||
12/14/2023 | COT - ENGR - Stormwater | N/A | Partial Pass | |
07/15/2024 | PDSD Site/Engineering Division - Landscaping | N/A | Partial Pass | I had a meeting with the contractor. He informed me that one of the doors are going to be required to change with wings on the side engineer of record will draw a change order up for it. |
11/07/2024 | ENGR Engineering Final | N/A | Partial Pass | Contractor needs to complete in placing the DG along the roadway on the West End |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0123-00124
Permit Description: Expansion of existing tile and granite manufacturing facility
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/21/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | Robin Hartman, Builder, Peter project engineer. Concentrating on building construction only at this time. Keep all materials within the site schedule inspections for Stormwater, trash enclosure, and accessibility inspections. | |
09/27/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
05/31/2024 | ENGR - Drainage Structures | Passed | No structure specified | |
05/31/2024 | SITE - Zoning Compliance | Passed | ||
11/07/2024 | COT - ENGR - Stormwater | Passed | ||
11/07/2024 | COT - SITE - Zoning Intermediate | Passed | ||
11/07/2024 | SITE - Stormwater Follow-up | Passed | ||
11/07/2024 | SITE - Stormwater Setup and Controls | Passed | ||
11/07/2024 | COT - ENGR - Signage Final | Passed | ||
11/07/2024 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
11/07/2024 | SITE - Stormwater Final Inspection | Passed | ||
11/07/2024 | SITE - Zoning Final | Passed | ||
11/07/2024 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed |