Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TD-DEV-0123-00101
Permit Details
Apply Date:
01/10/2023
Applicant:
Chris Hitchcock
Description:
New Freddy's Restaurant with drive-thru
Permit Reviews
Permit Number - TD-DEV-0123-00101
Permit Status: Complete
Permit Description: New Freddy's Restaurant with drive-thru
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/17/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 03/02/2023 | REQUIRES RESUBMIT |
06/07/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 07/10/2023 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0123-00101
Permite Description: New Freddy's Restaurant with drive-thru
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/01/2023 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No concerns at this time. Contractors are working on the installation of footers for the trash enclosure and portions of the building. No concerns for the stormwater. |
04/25/2024 | COT - ENGR - Stormwater | N/A | Partial Pass | Robin with Pate Scuppers are required were passing through a sidewalk. consult with Project engineer regarding changes |
05/03/2024 | ENGR - Drainage Structures | N/A | Not Ready | hey construction has been required to pull the bollard polls out and re-dig their locations 6 inches deeper or more to make sure we have enough concrete below the Baller tops. This work will be done first part of next week and a reinspection will be done to ensure everything is correct prior to pouring out the floor and the footer. |
06/20/2024 | ENGR Engineering Final | N/A | Partial Pass | engineering has no issues it would prevent a level four temporary certificate of occupancy |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0123-00101
Permit Description: New Freddy's Restaurant with drive-thru
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/30/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | 1) Details were gone over for the following; a) stormwater control implementation b) trash enclosure c) site maintenance d) inspections 2) Most wattle was in place previous to inspection, will need to be inspected every 2 weeks. 3) Plans were reviewed. 4) Signage for site SWPPP is in place. 5) Address is posted. |
|
06/11/2024 | COT - ENGR - Signage Final | Passed | ||
06/11/2024 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
06/11/2024 | SITE - Stormwater Final Inspection | Passed | ||
06/20/2024 | For trash and recycling enclosures | Passed | OK for level four TCO | |
07/23/2024 | ENGR Engineering Final | Passed | All items are complete. |