Permit: TC-RES-1224-07160
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
1147 E GRANT RD
Address NEW:
1147 E GRANT RD
Apply Date:
12/09/2024
Applicant:
Miguel Soto
Description:
Installation of Solar Panel System on workshop and garage roof and construction of Inverter Closet
Permit Reviews
Permit Number - TC-RES-1224-07160
Permit Status: Inspections
Permit Description: Installation of Solar Panel System on workshop and garage roof and construction of Inverter Closet
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/09/2025 | RESIDENTIAL SOLAR v.4 | 05/12/2025 | REQUIRES RESUBMIT |
| 02/21/2025 | RESIDENTIAL SOLAR v.2 | 02/21/2025 | REQUIRES RESUBMIT |
| 05/13/2025 | RESIDENTIAL SOLAR v.5 | 06/11/2025 | APPROVED |
| 12/11/2024 | RESIDENTIAL SOLAR v.1 | 01/09/2025 | REQUIRES RESUBMIT |
| 02/23/2025 | RESIDENTIAL SOLAR v.3 | 03/24/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-RES-1224-07160
Permit Status: Inspections
Permit Description: Installation of Solar Panel System on workshop and garage roof and construction of Inverter Closet
| Date | Description | Comments |
|---|---|---|
| 06/11/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-RES-1224-07160
Permite Description: Installation of Solar Panel System on workshop and garage roof and construction of Inverter Closet
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | |
| 03/06/2026 | RSBU - Building Final | N/A | Partial Pass | Partial pass for closet portion of permit, waiting PV |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-RES-1224-07160
Permit Description: Installation of Solar Panel System on workshop and garage roof and construction of Inverter Closet
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/22/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Ok to place concrete in footings. | |
| 03/06/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Closet finished awaiting PV |