Permit: TC-RES-1223-10085
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2901 E HAWTHORNE ST
Address NEW:
2901 E HAWTHORNE ST
Apply Date:
12/14/2023
Applicant:
Daniel Norman
Description:
INSTALLATION OF A 33 - 400W MODULE, 13.2kW DC / 13.1kW AZ SOLAR PV ARRAY MOUNTED ON NEW CARPORT CANOPY SHADE STRUCTURE.
Permit Reviews
Permit Number - TC-RES-1223-10085
Permit Status: Complete
Permit Description: INSTALLATION OF A 33 - 400W MODULE, 13.2kW DC / 13.1kW AZ SOLAR PV ARRAY MOUNTED ON NEW CARPORT CANOPY SHADE STRUCTURE.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 01/09/2026 | APPROVED |
| 07/01/2024 | RESIDENTIAL SOLAR v.1 | 07/01/2024 | REQUIRES RESUBMIT |
| 07/02/2024 | RESIDENTIAL SOLAR v.2 | 07/02/2024 | REQUIRES RESUBMIT |
| 04/17/2024 | RESIDENTIAL SOLAR v.3 | 05/20/2024 | REQUIRES RESUBMIT |
| 03/28/2024 | RESIDENTIAL SOLAR v.2 | 04/11/2024 | REQUIRES RESUBMIT |
| 12/14/2023 | RESIDENTIAL SOLAR v.1 | 01/11/2024 | REQUIRES RESUBMIT |
| 07/02/2024 | RESIDENTIAL SOLAR v.3 | 08/06/2024 | REQUIRES RESUBMIT |
| 08/19/2024 | RESIDENTIAL SOLAR v.4 | 09/16/2024 | APPROVED |
| 05/21/2024 | RESIDENTIAL SOLAR v.4 | 06/04/2024 | APPROVED |
| 12/23/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/26/2025 | REQUIRES RESUBMIT |
| 06/04/2024 | RESTAMP - RESIDENTIAL v.1 | 06/04/2024 | APPROVED |
Conditions
Permit Number - TC-RES-1223-10085
Permit Status: Complete
Permit Description: INSTALLATION OF A 33 - 400W MODULE, 13.2kW DC / 13.1kW AZ SOLAR PV ARRAY MOUNTED ON NEW CARPORT CANOPY SHADE STRUCTURE.
| Date | Description | Comments |
|---|---|---|
| 12/27/2023 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 12/27/2023 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1223-10085
Permite Description: INSTALLATION OF A 33 - 400W MODULE, 13.2kW DC / 13.1kW AZ SOLAR PV ARRAY MOUNTED ON NEW CARPORT CANOPY SHADE STRUCTURE.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/08/2024 | BULD - Electrical Clearance | N/A | Partial Pass | Partial for the 60A meter adapter, DGL Clearance was called into TEP at 11:30am Pending solar |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1223-10085
Permit Description: INSTALLATION OF A 33 - 400W MODULE, 13.2kW DC / 13.1kW AZ SOLAR PV ARRAY MOUNTED ON NEW CARPORT CANOPY SHADE STRUCTURE.
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/27/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Footings for steel columns are properly dug and columns in place. Okay to pour concrete. | |
| 09/27/2024 | COT - RSOL - Grounding/Bonding Solar Project | Passed | Column #1 is properly bonded to steel with 20' of #4 copper wire. | |
| 09/30/2024 | COT - RSOL - Electrical Underground Solar Project | Passed | Approved underground electrical from the service panel to the PV structure, okay to backfill progress areas | |
| 10/15/2024 | BULD - Electrical Clearance | Passed | CLEAR DGC | |
| 10/15/2024 | RSBU - Building Progress | Passed | ||
| 10/15/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 10/15/2024 | COT - RSOL - Electrical Progress Solar Project | Passed | ||
| 10/15/2024 | COT - RSOL - Electrical Final Solar Project | Passed | Project complete. | |
| 10/15/2024 | RSBU - Building Final | Passed | Project complete. CLOSE PERMIT |