Permit: TC-RES-1122-01058
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
1346 S 4TH AV
Address NEW:
1346 S 4TH AV
Apply Date:
11/23/2022
Applicant:
Chris Steele
Description:
Duplex
Permit Reviews
Permit Number - TC-RES-1122-01058
Permit Status: Inspections complete
Permit Description: Duplex
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/07/2023 | RESIDENTIAL NEW DWELLING v.2 | 03/02/2023 | REQUIRES RESUBMIT |
| 05/10/2023 | RESTAMP - RESIDENTIAL v.1 | 05/11/2023 | APPROVED |
| 07/21/2023 | RESTAMP - RESIDENTIAL v.1 | 07/24/2023 | APPROVED |
| 12/20/2022 | RESIDENTIAL NEW DWELLING v.1 | 01/05/2023 | REQUIRES RESUBMIT |
| 08/03/2023 | RESIDENTIAL NEW DWELLING v.1 | 08/03/2023 | REQUIRES RESUBMIT |
| 05/10/2023 | RESIDENTIAL NEW DWELLING v.4 | 05/10/2023 | APPROVED |
| 04/03/2023 | RESIDENTIAL NEW DWELLING v.3 | 04/26/2023 | REQUIRES RESUBMIT |
| 08/14/2023 | RESIDENTIAL NEW DWELLING v.2 | 08/29/2023 | APPROVED |
| 08/29/2023 | RESTAMP - RESIDENTIAL v.1 | 08/29/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-RES-1122-01058
Permit Status: Inspections complete
Permit Description: Duplex
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/05/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-RES-1122-01058
Permit Status: Inspections complete
Permit Description: Duplex
| Date | Description | Comments |
|---|---|---|
| 04/26/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-1122-01058
Permite Description: Duplex
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2023 | COT - RSBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
| 08/06/2024 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 11/28/2023 | COT - BULD - SWG Clearance | N/A | Not Ready |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-1122-01058
Permit Description: Duplex
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/26/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Footings are dug 12" below grade, rebar reinforcement is installed per plans. Okay to concrete footings. | |
| 07/26/2023 | COT - RSEL - Grounding/Bonding | Passed | #4 copper wire is attached to #4 rebar reinforcement in bottom of footer for the ufer ground. | |
| 08/01/2023 | COT - RSBU - Stem Wall/Retaining Wall | Passed | ||
| 08/11/2023 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 8/11/2023 | |
| 09/07/2023 | COT - RSBU - Masonry Pregrout | Passed | ||
| 10/10/2023 | COT - RSBU - Roof Nailing | Passed | ||
| 10/10/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 10/26/2023 | BULD - Electrical Clearance | Passed | TEP eco | |
| 10/26/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 11/21/2023 | COT - RSPL - Yard Water Line | Passed | ||
| 11/28/2023 | COT - RSPL - Gas Pressure Test | Passed | Approved gas piping and pressure test for both units of the duplex, okay to backfill progress areas (duplex) | |
| 12/18/2023 | COT - RSPL - Sewer | Passed | ||
| 08/06/2024 | ENGR Engineering Final | Passed | On building 2 please remove abandoned wording for the 1930s light pole. | |
| 08/06/2024 | COT - RSBU - Preslab | Passed | ||
| 08/12/2024 | COT - BULD - SWG Clearance | Passed | Request meter sets for units #1 and #2. | |
| 08/12/2024 | RSBU - Building Final | Passed | ||
| 08/12/2024 | COT - RSEL - Electrical Final | Passed | ||
| 08/12/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 08/12/2024 | COT - RSME - Mechanical Final | Passed | ||
| 08/12/2024 | COT - RSPL - Plumbing Final | Passed |