Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
835 N 1ST AV
Address NEW:
835 N 1ST AV
Apply Date:
10/01/2023
Applicant:
Juan Figueroa
Description:
CE-VIO0723-04376 - Renovate Duplex

Permit Reviews

Permit Number - TC-RES-1023-08449
Permit Status: Inspections
Permit Description: CE-VIO0723-04376 - Renovate Duplex
Start Date Submittal Complete Date Status  
10/04/2023 RESIDENTIAL NEW DWELLING v.1 11/01/2023 REQUIRES RESUBMIT Review Details
01/26/2024 RESIDENTIAL NEW DWELLING v.3 02/16/2024 REQUIRES RESUBMIT Review Details
11/29/2023 RESIDENTIAL NEW DWELLING v.2 12/20/2023 REQUIRES RESUBMIT Review Details
06/28/2024 RESIDENTIAL NEW DWELLING v.4 07/30/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-RES-1023-08449
Permite Description: CE-VIO0723-04376 - Renovate Duplex
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
11/13/2025 COT - RSEL - Grounding/Bonding N/A Re-inspection required 11/13/25: Inspection were never called in during time of construction, please provide proper documentation of 1-hour fire rated assembly, electrical not per plan (missing circuits throughout, multiple circuits tied together), receptacle spacing at kitchen countertop and wall space none code compliant. Exhaust fan missing at upstairs unit bathroom, piping at bathroom vanity none code compliant. Properly secure all exterior raceways at main panel, insulation required at exterior domestic supply lines, light fixtures at basement must be rated for the application, roof access required for final, laundry/storage room has been demolished (revision required), windows must be tested to open to meet egress requirements, smoke alarms must be 3' from air supplies and fan fixtures, water hammer arrestor required at refrigerator, hot water heaters were not inspected, ac units were not inspected. Letters from licensed contractor required prior to final for plumbing work, electrical work, mechanical work, framing work completed prior to the completion of any inspections.
11/13/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required 11/13/25: Inspection were never called in during time of construction, please provide proper documentation of 1-hour fire rated assembly, electrical not per plan (missing circuits throughout, multiple circuits tied together), receptacle spacing at kitchen countertop and wall space none code compliant. Exhaust fan missing at upstairs unit bathroom, piping at bathroom vanity none code compliant. Properly secure all exterior raceways at main panel, insulation required at exterior domestic supply lines, light fixtures at basement must be rated for the application, roof access required for final, laundry/storage room has been demolished (revision required), windows must be tested to open to meet egress requirements, smoke alarms must be 3' from air supplies and fan fixtures, water hammer arrestor required at refrigerator, hot water heaters were not inspected, ac units were not inspected. Letters from licensed contractor required prior to final for plumbing work, electrical work, mechanical work, framing work completed prior to the completion of any inspections.
11/13/2025 COT - RSME - Mechanical Final N/A Re-inspection required 11/13/25: Inspection were never called in during time of construction, please provide proper documentation of 1-hour fire rated assembly, electrical not per plan (missing circuits throughout, multiple circuits tied together), receptacle spacing at kitchen countertop and wall space none code compliant. Exhaust fan missing at upstairs unit bathroom, piping at bathroom vanity none code compliant. Properly secure all exterior raceways at main panel, insulation required at exterior domestic supply lines, light fixtures at basement must be rated for the application, roof access required for final, laundry/storage room has been demolished (revision required), windows must be tested to open to meet egress requirements, smoke alarms must be 3' from air supplies and fan fixtures, water hammer arrestor required at refrigerator, hot water heaters were not inspected, ac units were not inspected. Letters from licensed contractor required prior to final for plumbing work, electrical work, mechanical work, framing work completed prior to the completion of any inspections.
11/13/2025 COT - RSBU - Firewall/Fire Barrier/Firestop N/A Re-inspection required 11/13/25: Inspection were never called in during time of construction, please provide proper documentation of 1-hour fire rated assembly, electrical not per plan (missing circuits throughout, multiple circuits tied together), receptacle spacing at kitchen countertop and wall space none code compliant. Exhaust fan missing at upstairs unit bathroom, piping at bathroom vanity none code compliant. Properly secure all exterior raceways at main panel, insulation required at exterior domestic supply lines, light fixtures at basement must be rated for the application, roof access required for final, laundry/storage room has been demolished (revision required), windows must be tested to open to meet egress requirements, smoke alarms must be 3' from air supplies and fan fixtures, water hammer arrestor required at refrigerator, hot water heaters were not inspected, ac units were not inspected. Letters from licensed contractor required prior to final for plumbing work, electrical work, mechanical work, framing work completed prior to the completion of any inspections.
11/13/2025 RSBU - Building Final N/A Re-inspection required 11/13/25: Inspection were never called in during time of construction, please provide proper documentation of 1-hour fire rated assembly, electrical not per plan (missing circuits throughout, multiple circuits tied together), receptacle spacing at kitchen countertop and wall space none code compliant. Exhaust fan missing at upstairs unit bathroom, piping at bathroom vanity none code compliant. Properly secure all exterior raceways at main panel, insulation required at exterior domestic supply lines, light fixtures at basement must be rated for the application, roof access required for final, laundry/storage room has been demolished (revision required), windows must be tested to open to meet egress requirements, smoke alarms must be 3' from air supplies and fan fixtures, water hammer arrestor required at refrigerator, hot water heaters were not inspected, ac units were not inspected. Letters from licensed contractor required prior to final for plumbing work, electrical work, mechanical work, framing work completed prior to the completion of any inspections.
11/13/2025 COT - RSPL - Plumbing Final N/A Re-inspection required 11/13/25: Inspection were never called in during time of construction, please provide proper documentation of 1-hour fire rated assembly, electrical not per plan (missing circuits throughout, multiple circuits tied together), receptacle spacing at kitchen countertop and wall space none code compliant. Exhaust fan missing at upstairs unit bathroom, piping at bathroom vanity none code compliant. Properly secure all exterior raceways at main panel, insulation required at exterior domestic supply lines, light fixtures at basement must be rated for the application, roof access required for final, laundry/storage room has been demolished (revision required), windows must be tested to open to meet egress requirements, smoke alarms must be 3' from air supplies and fan fixtures, water hammer arrestor required at refrigerator, hot water heaters were not inspected, ac units were not inspected. Letters from licensed contractor required prior to final for plumbing work, electrical work, mechanical work, framing work completed prior to the completion of any inspections.
11/13/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required 11/13/25: Inspection were never called in during time of construction, please provide proper documentation of 1-hour fire rated assembly, electrical not per plan (missing circuits throughout, multiple circuits tied together), receptacle spacing at kitchen countertop and wall space none code compliant. Exhaust fan missing at upstairs unit bathroom, piping at bathroom vanity none code compliant. Properly secure all exterior raceways at main panel, insulation required at exterior domestic supply lines, light fixtures at basement must be rated for the application, roof access required for final, laundry/storage room has been demolished (revision required), windows must be tested to open to meet egress requirements, smoke alarms must be 3' from air supplies and fan fixtures, water hammer arrestor required at refrigerator, hot water heaters were not inspected, ac units were not inspected. Letters from licensed contractor required prior to final for plumbing work, electrical work, mechanical work, framing work completed prior to the completion of any inspections.
11/13/2025 COT - RSEL - Electrical Final N/A Re-inspection required 11/13/25: Inspection were never called in during time of construction, please provide proper documentation of 1-hour fire rated assembly, electrical not per plan (missing circuits throughout, multiple circuits tied together), receptacle spacing at kitchen countertop and wall space none code compliant. Exhaust fan missing at upstairs unit bathroom, piping at bathroom vanity none code compliant. Properly secure all exterior raceways at main panel, insulation required at exterior domestic supply lines, light fixtures at basement must be rated for the application, roof access required for final, laundry/storage room has been demolished (revision required), windows must be tested to open to meet egress requirements, smoke alarms must be 3' from air supplies and fan fixtures, water hammer arrestor required at refrigerator, hot water heaters were not inspected, ac units were not inspected. Letters from licensed contractor required prior to final for plumbing work, electrical work, mechanical work, framing work completed prior to the completion of any inspections.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-RES-1023-08449
Permit Description: CE-VIO0723-04376 - Renovate Duplex
Total Completed Inspections - 1
Date Description Inspector Results Comments
09/20/2024 BULD - Electrical Clearance Passed Approved 200A service panel upgrade - INCR Clearance to TEP is required for the cutover at 835 N 1st Av and 837 N 1st Av
Pending final - NR

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-TC-RES-1023-08449 RESUBMISSION V.2_V4.PDF DOCUMENTS VIEW