Permit: TC-RES-0626-03424
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
2220 N ARENA VISTA AV UNIT 2
Address NEW:
2220 N ARENA VISTA AV UNIT 2
Apply Date:
06/23/2026
Applicant:
Bradley Jones
Description:
ADU
Permit Reviews
Permit Number - TC-RES-0626-03424
Permit Status: Issued
Permit Description: ADU
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/15/2026 | ADMINISTRATIVE v.1 | 09/15/2026 | REQUIRES RESUBMIT |
| 09/10/2026 | RESIDENTIAL ADU v.4 | 09/15/2026 | APPROVED |
| 08/20/2026 | RESIDENTIAL ADU v.2 | N/A | REQUIRES RESUBMIT |
| 09/08/2026 | RESIDENTIAL ADU v.3 | 09/08/2026 | REQUIRES RESUBMIT |
| 11/05/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/05/2026 | APPROVED |
| 06/25/2026 | RESIDENTIAL ADU v.1 | 06/30/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-RES-0626-03424
Permit Status: Issued
Permit Description: ADU
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/30/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
Conditions
Permit Number - TC-RES-0626-03424
Permit Status: Issued
Permit Description: ADU
| Date | Description | Comments |
|---|---|---|
| 06/30/2026 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 06/30/2026 | Manual J report | |
| 06/30/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-RES-0626-03424
Permite Description: ADU
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/30/2026 | ENGR Engineering Final | N/A | Not Ready | |
| 10/30/2026 | COT - RSPL - Gas Pressure Test | N/A | Partial Pass | OK to cover, however be aware of the conditions below: Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
| 10/30/2026 | COT - RSEL - Grounding/Bonding | N/A | Partial Pass | underslab ufer. Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
| 10/30/2026 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Re-inspection required | Porch footings are less than 12” into undisturbed soil. |
| 10/30/2026 | COT - RSBU - Preslab | N/A | Re-inspection required | Porch footings are less than 12” into undisturbed soil. |
| 10/30/2026 | COT - RSEL - Electrical Underground | N/A | Re-inspection required | Sub-panel conduit is smaller than shown on approved plans. |
| 11/16/2026 | COT - RSBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | 11/16/2026 Not ready. Call in at drywall. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-RES-0626-03424
Permit Description: ADU
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/22/2026 | COT - RSPL - Rough Soil | Passed | Passed | |
| 10/22/2026 | COT - RSPL - Sewer | Passed | Passed | |
| 10/22/2026 | COT - RSPL - Yard Water Line | Passed | Passed | |
| 11/05/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 11.5.26 Pass, all corrections made. |
|
| 11/05/2026 | COT - RSBU - Preslab | Passed | ||
| 11/05/2026 | COT - RSEL - Electrical Underground | Passed | No Ufer at this time; 2” conduit southeast side of house for main or subpanel and 1” conduit just north of the 2inch for island. | |
| 11/17/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 11/17/2026 All corrections made. Okay to proceed. |
|
| 11/17/2026 | COT - RSBU - Roof Nailing | Passed | 11/17/2026 All corrections made. Okay to proceed. |