Residential Building - One or Two Family
Apply Date:
03/27/2025
Applicant:
Lu Griego
Description:
Bedroom Suite Addition REV1_1. Roof Structure Revision The previously approved plan set utilized pre-fabricated trusses (see approved Roof Plan). The revised submittal replaces the truss system with a conventional wood-framed rafter system. - Rafters are clearly indicated on the Roof / Framing Plan (Sheet A104) - Roof slope, spacing, and structural members have been updated accordingly - All related framing details have been revised to reflect this system 2. Beam and Post Structural Support Due to the change from trusses to rafters, a beam and post support system has been introduced. - Beam support is provided along the wall lines to carry roof loads - Posts transfer loads to the foundation - Structural connections are shown in the updated details Refer to: - Foundation Plan – Detail 2 (Post Column Footing) - Roof Plan / Framing Details – Sheet A104 (Beam + Rafter Connections) 3. Coordination with Structural and Foundation Elements All affected sheets have been coordinated to reflect the revised system, including: - Foundation Plan (updated for post supports) - Roof / Framing Plan (rafters in lieu of trusses) - Structural details and connections 4. Clarification This revision is a design change from truss system to rafter framing, not an omission. All required structural elements and load paths are fully detailed within the submitted plans.

Permit Reviews

Permit Number - TC-RES-0325-01617
Permit Status: Inspections
Permit Description: Bedroom Suite Addition REV1_1. Roof Structure Revision The previously approved plan set utilized pre-fabricated trusses (see approved Roof Plan). The revised submittal replaces the truss system with a conventional wood-framed rafter system. - Rafters are clearly indicated on the Roof / Framing Plan (Sheet A104) - Roof slope, spacing, and structural members have been updated accordingly - All related framing details have been revised to reflect this system 2. Beam and Post Structural Support Due to the change from trusses to rafters, a beam and post support system has been introduced. - Beam support is provided along the wall lines to carry roof loads - Posts transfer loads to the foundation - Structural connections are shown in the updated details Refer to: - Foundation Plan – Detail 2 (Post Column Footing) - Roof Plan / Framing Details – Sheet A104 (Beam + Rafter Connections) 3. Coordination with Structural and Foundation Elements All affected sheets have been coordinated to reflect the revised system, including: - Foundation Plan (updated for post supports) - Roof / Framing Plan (rafters in lieu of trusses) - Structural details and connections 4. Clarification This revision is a design change from truss system to rafter framing, not an omission. All required structural elements and load paths are fully detailed within the submitted plans.
Start Date Submittal Complete Date Status  
04/07/2025 RESIDENTIAL NEW DWELLING v.1 04/07/2025 REQUIRES RESUBMIT Review Details
03/25/2026 RESIDENTIAL NEW DWELLING REVISION v.1 04/08/2026 REQUIRES RESUBMIT Review Details
08/13/2025 RESIDENTIAL NEW DWELLING v.4 08/13/2025 REQUIRES RESUBMIT Review Details
01/30/2026 RESIDENTIAL NEW DWELLING v.5 02/13/2026 APPROVED Review Details
05/19/2025 RESIDENTIAL NEW DWELLING v.3 06/20/2025 REQUIRES RESUBMIT Review Details
04/27/2026 RESIDENTIAL NEW DWELLING REVISION v.3 04/28/2026 APPROVED Review Details
04/09/2025 RESIDENTIAL NEW DWELLING v.2 05/12/2025 REQUIRES RESUBMIT Review Details
04/23/2026 RESIDENTIAL NEW DWELLING REVISION v.2 N/A REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-RES-0325-01617
Permit Status: Inspections
Permit Description: Bedroom Suite Addition REV1_1. Roof Structure Revision The previously approved plan set utilized pre-fabricated trusses (see approved Roof Plan). The revised submittal replaces the truss system with a conventional wood-framed rafter system. - Rafters are clearly indicated on the Roof / Framing Plan (Sheet A104) - Roof slope, spacing, and structural members have been updated accordingly - All related framing details have been revised to reflect this system 2. Beam and Post Structural Support Due to the change from trusses to rafters, a beam and post support system has been introduced. - Beam support is provided along the wall lines to carry roof loads - Posts transfer loads to the foundation - Structural connections are shown in the updated details Refer to: - Foundation Plan – Detail 2 (Post Column Footing) - Roof Plan / Framing Details – Sheet A104 (Beam + Rafter Connections) 3. Coordination with Structural and Foundation Elements All affected sheets have been coordinated to reflect the revised system, including: - Foundation Plan (updated for post supports) - Roof / Framing Plan (rafters in lieu of trusses) - Structural details and connections 4. Clarification This revision is a design change from truss system to rafter framing, not an omission. All required structural elements and load paths are fully detailed within the submitted plans.
Total Outstanding Activity Conditions - 2
Date Name
05/05/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
11/19/2025 Submission of the final Elevation Certificate and completion of the Floodplain Use Permit is required PRIOR TO FINALING this permit.

Conditions

Permit Number - TC-RES-0325-01617
Permit Status: Inspections
Permit Description: Bedroom Suite Addition REV1_1. Roof Structure Revision The previously approved plan set utilized pre-fabricated trusses (see approved Roof Plan). The revised submittal replaces the truss system with a conventional wood-framed rafter system. - Rafters are clearly indicated on the Roof / Framing Plan (Sheet A104) - Roof slope, spacing, and structural members have been updated accordingly - All related framing details have been revised to reflect this system 2. Beam and Post Structural Support Due to the change from trusses to rafters, a beam and post support system has been introduced. - Beam support is provided along the wall lines to carry roof loads - Posts transfer loads to the foundation - Structural connections are shown in the updated details Refer to: - Foundation Plan – Detail 2 (Post Column Footing) - Roof Plan / Framing Details – Sheet A104 (Beam + Rafter Connections) 3. Coordination with Structural and Foundation Elements All affected sheets have been coordinated to reflect the revised system, including: - Foundation Plan (updated for post supports) - Roof / Framing Plan (rafters in lieu of trusses) - Structural details and connections 4. Clarification This revision is a design change from truss system to rafter framing, not an omission. All required structural elements and load paths are fully detailed within the submitted plans.
Date Description Comments
04/08/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-MOUNTAIN_ADD_CD_SET_V3.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-BURROLA_ADDIITON_CONS-PLAN_SET_5_V5.PDF DOCUMENTS VIEW
PERMIT_RESPONSE_LETTER_UNIT1_SITE_ENGINEERING_REVISED_V3.PDF DOCUMENTS VIEW