Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-RES-0124-00101
Permit Details
Apply Date:
01/05/2024
Applicant:
Terry Darr
Description:
SFR
Permit Reviews
Permit Number - TC-RES-0124-00101
Permit Status: Issued
Permit Description: SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/29/2024 | RESTAMP - RESIDENTIAL v.1 | 05/01/2024 | APPROVED |
01/05/2024 | RESIDENTIAL NEW DWELLING v.1 | 02/01/2024 | REQUIRES RESUBMIT |
07/30/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/01/2024 | APPROVED |
04/05/2024 | RESIDENTIAL NEW DWELLING v.2 | 04/29/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-RES-0124-00101
Permit Status: Issued
Permit Description: SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/21/2024 | Post-Tension Inspection Report is required. |
Conditions
Permit Number - TC-RES-0124-00101
Permit Status: Issued
Permit Description: SFR
Date | Description | Comments |
---|---|---|
04/21/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/22/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-RES-0124-00101
Permite Description: SFR
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/31/2024 | COT - RSBU - Roof Nailing | N/A | Not Ready | Not ready no extension ladder on site |
07/31/2024 | COT - RSBU - Exterior Clips/Sheathing | N/A | Not Ready | Not ready hold down is not in place stopped inspection |
02/19/2025 | BULD - Electrical Clearance | N/A | Re-inspection required | 2/19/25: Grey water not installed per plans, properly support gas lines in wall at garage, DWV not under test, support pex lines at laundry in wall for laundry box, nail plates required where electrical or plumbing comes within 1 1/4" of face of stud, supply air missing in laundry room, supply air missing in hall way, secure pex at hose bib, nail plate required at kitchen hood duct, fire place vent not installed, gas piping not complete, seal all penetrations at top plate throughout, copper pipe that will be in contact with stucco must be wrapped with 10mil tape for uv protection. STOPPED INSPECTION WILL BE RECALLED WHEN COMPLETED. |
02/19/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 2/19/25: Grey water not installed per plans, properly support gas lines in wall at garage, DWV not under test, support pex lines at laundry in wall for laundry box, nail plates required where electrical or plumbing comes within 1 1/4" of face of stud, supply air missing in laundry room, supply air missing in hall way, secure pex at hose bib, nail plate required at kitchen hood duct, fire place vent not installed, gas piping not complete, seal all penetrations at top plate throughout, copper pipe that will be in contact with stucco must be wrapped with 10mil tape for uv protection. STOPPED INSPECTION WILL BE RECALLED WHEN COMPLETED. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-RES-0124-00101
Permit Description: SFR
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/17/2024 | COT - RSPL - Rough Soil | Passed | 5/17/24: plumbing underground per plans ok to backfill. Shading required | |
06/05/2024 | COT - RSBU - Preslab | Passed | 6/5/24: reinforcement per schedule ok to proceed. | |
06/05/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 6/5/24: reinforcement per schedule ok to proceed. | |
07/05/2024 | COT - RSPL - Sewer | Passed | 7/5/24: sewer connection made. Ok to backfill. Shading required | |
08/02/2024 | COT - RSBU - Roof Nailing | Passed | Not ready no extension ladder on site 8/2/24: roof nailing passed ok to dry-in |
|
08/30/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Ok to,cover exterior walls | |
12/20/2024 | COT - RSPL - Yard Water Line | Passed | 12/20/24 pass ok to backfill, shading required. | |
02/25/2025 | COT - RSPL - Gas Pressure Test | Passed | 2/25/25 Corrections made held pressure | |
02/25/2025 | BULD - Electrical Clearance | Passed | 2/25/25 Corrections made CLEARANCE ECO ready for temp power | |
02/25/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 2/25/25 corrections made |