Permit: TC-MDP-1225-00768
Permit Details
Status:
Inspections
Type:
Model Building Permit
Address:
402 W COLUMBIA ST UNIT 1
Address NEW:
402 W COLUMBIA ST UNIT 1
Apply Date:
12/18/2025
Applicant:
Carlos Brown
Description:
Duplex MDL Charly (Model Master Plan TC-MDP-1025-00706)
Permit Reviews
Permit Number - TC-MDP-1225-00768
Permit Status: Inspections
Permit Description: Duplex MDL Charly (Model Master Plan TC-MDP-1025-00706)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/23/2026 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 02/02/2026 | APPROVED |
| 02/02/2026 | ADMINISTRATIVE v.1 | 02/02/2026 | REQUIRES RESUBMIT |
| 02/20/2026 | ADMINISTRATIVE v.2 | N/A | APPROVED |
| 12/22/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 01/08/2026 | REQUIRES RESUBMIT |
| 02/19/2026 | ADMINISTRATIVE v.1 | N/A | REQUIRES RESUBMIT |
| 02/19/2026 | ADMINISTRATIVE v.2 | N/A | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1225-00768
Permit Status: Inspections
Permit Description: Duplex MDL Charly (Model Master Plan TC-MDP-1025-00706)
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/09/2025 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
Conditions
Permit Number - TC-MDP-1225-00768
Permit Status: Inspections
Permit Description: Duplex MDL Charly (Model Master Plan TC-MDP-1025-00706)
| Date | Description | Comments |
|---|---|---|
| 12/22/2025 | Plans show Unit 1 and Unit 2. Please contact Pima County Addressing to add the Unit numbers to the property address at Addressing@pima.gov or 520-724-9512 | |
| 12/09/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 12/09/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 12/09/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-MDP-1225-00768
Permite Description: Duplex MDL Charly (Model Master Plan TC-MDP-1025-00706)
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2026 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
| 02/24/2026 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 02/24/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 02/26/2026 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 2/26/2026 Partial pass pending revision for relocation of water service. Okay to proceed. |
| 03/05/2026 | COT - RSBU - Roof Nailing | N/A | Re-inspection required | 3-5-26: roof nailing-add nails at marked locations. I was not able to thoroughly inspect south unit due to framers occupying space working. Please reschedule & provide approved plans together with truss calculations. |
| 03/06/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Re-inspection required | 3-6-26: add nails to exterior sheathing at marked locations but have framers re-walk it nd add nails according to plans, add shot pins at 24" o.c.-minimum of 2 per plate and must be installed within 6" from the end of both ends of plate, add anchor bolts to marked locations-a/b's must be installed in middle third of plate and at 32" o.c., add A35's to cross bracing-see plans for information. |
| 03/10/2026 | COT - RSBU - Interior Shear Bracing | N/A | Partial Pass | 3-10-26: okay to install 5/8" drywall at exterior side. We will use this inspection to verify drywall screw prior to units being taped & textured. |
| 03/11/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-1225-00768
Permit Description: Duplex MDL Charly (Model Master Plan TC-MDP-1025-00706)
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2026 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 2/24/2026 | |
| 02/24/2026 | RSBU - Building Progress | Passed | ||
| 02/26/2026 | COT - RSBU - Preslab | Passed | 2/26/2026 Approved per plan and foundation details. Okay for concrete placement. |
|
| 03/06/2026 | COT - RSBU - Roof Nailing | Passed | 3-6-26: okay to dry-in roof. | |
| 03/10/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 3-10-26: exterior clips/sheathing approved. |