Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
09/12/2024
Applicant:
Abraham Andraux
Description:
GRANDE DUPLEX MODEL PLAN SET (Model Master Plan TC-MDP-0623-01113)

Permit Reviews

Permit Number - TC-MDP-1123-01835
Permit Status: Complete
Permit Description: GRANDE DUPLEX MODEL PLAN SET (Model Master Plan TC-MDP-0623-01113)
Start Date Submittal Complete Date Status  
11/28/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/01/2025 APPROVED Review Details
04/22/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 05/06/2025 APPROVED Review Details
09/18/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 10/02/2024 REQUIRES RESUBMIT Review Details
04/21/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 04/21/2025 REQUIRES RESUBMIT Review Details
04/15/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 04/15/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-MDP-1123-01835
Permit Status: Complete
Permit Description: GRANDE DUPLEX MODEL PLAN SET (Model Master Plan TC-MDP-0623-01113)
Date Description Comments
11/04/2025 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.
04/21/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
06/02/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
11/04/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-1123-01835
Permite Description: GRANDE DUPLEX MODEL PLAN SET (Model Master Plan TC-MDP-0623-01113)
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
06/06/2025 COT - RSBU - Interior Shear Bracing N/A Not Applicable N/A
07/21/2025 COT - RSEL - Electrical Underground N/A Not Applicable
07/21/2025 COT - RSPL - Gas Pressure Test N/A Not Applicable
07/21/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required 7/21/2025 per previous notes. Engineer fix has to be uploaded to portal with an approved fix. Dry wall is in place.
07/25/2025 COT - RSPL - Yard Water Line N/A Re-inspection required 7-25-2025: Not ready
07/24/2025 BULD - Electrical Clearance N/A Re-inspection required Not ready. Meter base has been painted. It cannot be cleaned and has to be replaced. 7/24/2025
08/05/2025 COT - BULD - SWG Clearance N/A Not Applicable site does not use gas
07/21/2025 COT - RSEL - Grounding/Bonding N/A Re-inspection required Per previous notes. 7/21/2025
07/21/2025 COT - RSEL - Outdoor Lighting N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-1123-01835
Permit Description: GRANDE DUPLEX MODEL PLAN SET (Model Master Plan TC-MDP-0623-01113)
Total Completed Inspections - 16
Date Description Inspector Results Comments
05/27/2025 COT - RSPL - Rough Soil Passed 5/23/25
No plumbing plans on site, or electronically.
5/27/25:plumbing per approved plans ok to proceed with backfill. Shading required
05/29/2025 COT - RSBU - Preslab Passed
05/29/2025 COT - RSBU - Excavation/Rebar/Zoning Passed
06/06/2025 COT - RSBU - Roof Nailing Passed
06/23/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 6-23-25: grey water verified. Okay to continue with construction.
07/21/2025 RSBU - Building Progress Passed
07/24/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
07/30/2025 BULD - Electrical Clearance Passed 7/30/25
TEP CLEARANCE: ECO, UNITS 1,2,3,4.
07/31/2025 COT - RSPL - Sewer Passed Approved 4" sewer piping from duplex unit to HCS at street, okay to shade fill progress areas
08/05/2025 RSBU - Building Final Passed Passed final 8/5/25
08/05/2025 COT - RSEL - Electrical Final Passed Passed final 8/5/25
08/05/2025 COT - RSEL - Grounding/Bonding Passed
08/05/2025 COT - RSEL - Outdoor Lighting Passed Passed final 8/5/25
08/05/2025 COT - RSME - Mechanical Final Passed Passed final 8/5/25
08/05/2025 COT - RSPL - Plumbing Final Passed Passed final 8/5/25
10/17/2025 ENGR Engineering Final Passed Site is complete in accordance with approved plans. Buildings are safe and accessible. Engineering is okay for CofO.

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL (SSRS).PDF DOCUMENTS VIEW
1603 VAN BUREN UNITS 34 LEAKAGE AND DUCT TEST_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
2_DEVELOPMENT PACKAGE FOR 1603 S VAN BUREN AV_V1 (1)_V2.PDF DOCUMENTS VIEW