Permit: TC-MDP-1025-00611
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
2157 E SUPERSONIC ST
Address NEW:
2157 E SUPERSONIC ST
Apply Date:
05/21/2026
Applicant:
Celina Rodriguez
Description:
Cielo Reserves 1740 Model Plan (Model master plan TC-MDP-0625-00360)
Permit Reviews
Permit Number - TC-MDP-1025-00611
Permit Status: Inspections complete
Permit Description: Cielo Reserves 1740 Model Plan (Model master plan TC-MDP-0625-00360)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/30/2026 | SPECIAL INSPECTION REVIEW v.1 | 09/30/2026 | APPROVED |
| 05/26/2026 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 05/29/2026 | APPROVED |
Conditions
Permit Number - TC-MDP-1025-00611
Permit Status: Inspections complete
Permit Description: Cielo Reserves 1740 Model Plan (Model master plan TC-MDP-0625-00360)
| Date | Description | Comments |
|---|---|---|
| 05/26/2026 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 05/26/2026 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 10/02/2025 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 10/02/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 10/02/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1025-00611
Permite Description: Cielo Reserves 1740 Model Plan (Model master plan TC-MDP-0625-00360)
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2026 | COT - RSPL - Gas Pressure Test | N/A | Not Ready | Roof not dried in. 7/20/2026 |
| 07/20/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | Roof not dried in. 7/20/2026 |
| 09/22/2026 | ENGR Engineering Final | N/A | Partial Pass | Site is complete. Unsatisfied conditions not approved prior to final. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1025-00611
Permit Description: Cielo Reserves 1740 Model Plan (Model master plan TC-MDP-0625-00360)
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/17/2026 | COT - RSPL - Rough Soil | Passed | ||
| 06/17/2026 | COT - RSPL - Sewer | Passed | ||
| 06/17/2026 | COT - RSPL - Yard Water Line | Passed | ||
| 06/26/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 06/26/2026 | COT - RSBU - Preslab | Passed | ||
| 06/26/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 07/14/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 07/14/2026 Corrections made. |
|
| 07/14/2026 | COT - RSBU - Roof Nailing | Passed | 07/14/2026 Corrections made. |
|
| 07/21/2026 | COT - RSPL - Gas Pressure Test | Passed | ||
| 07/21/2026 | RSBU - Building Progress | Passed | ||
| 07/23/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 7/23/2026 all corrections were made. | |
| 07/28/2026 | COT - RSBU - Interior Shear Bracing | Passed | 7-28-26 okay to cover | |
| 08/04/2026 | BULD - Electrical Clearance | Passed | 08/04/2026 Clearance for TEP ECO. |
|
| 09/02/2026 | COT - BULD - SWG Clearance | Passed | 9-2-26 SWG clearance approved | |
| 09/21/2026 | COT - RSEL - Outdoor Lighting | Passed | 9/21/26: outdoor lighting approved. | |
| 09/22/2026 | COT - RSEL - Electrical Final | Passed | 9-22-26 electrical final approved | |
| 09/22/2026 | COT - RSME - Mechanical Final | Passed | 9-22-26 All corrections have been made mechanical final approved | |
| 09/22/2026 | COT - RSPL - Plumbing Final | Passed | 9-22-26 plumbing final approved | |
| 10/01/2026 | ENGR Engineering Final | Passed | ||
| 10/02/2026 | RSBU - Building Final | Passed |