Permit: TC-MDP-1024-01242
Permit Details
Apply Date:
10/28/2024
Applicant:
Mark Alteri
Description:
PV 1074 SFR
Permit Reviews
Permit Number - TC-MDP-1024-01242
Permit Status: In review
Permit Description: PV 1074 SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/10/2025 | APPROVED |
10/29/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 11/15/2024 | APPROVED |
01/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | N/A | IN REVIEW |
Outstanding Activity Conditions
Permit Number - TC-MDP-1024-01242
Permit Status: In review
Permit Description: PV 1074 SFR
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
10/23/2024 | Post-Tension Inspection Report is required. |
10/29/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
12/18/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Conditions
Permit Number - TC-MDP-1024-01242
Permit Status: In review
Permit Description: PV 1074 SFR
Date | Description | Comments |
---|---|---|
11/19/2024 | The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account. | |
10/23/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
10/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
10/23/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
12/18/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: In Review
Permit Number: TC-MDP-1024-01242
Permite Description: PV 1074 SFR
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/02/2024 | COT - RSEL - Grounding/Bonding | N/A | Partial Pass | |
12/03/2024 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Re-inspection required | Partial pass. Pending plumbing wrap. 12/2/2024 12/3/24: per previous notes. |
12/03/2024 | COT - RSBU - Preslab | N/A | Re-inspection required | Partial pass. Pending plumbing wrap. 12/2/2024 12/3/24: per previous notes |
Completed Inspections
Permit Status: In Review
Permit Number: TC-MDP-1024-01242
Permit Description: PV 1074 SFR
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/19/2024 | COT - RSPL - Rough Soil | Passed | 11/22/24 pass | |
11/22/2024 | COT - RSPL - Sewer | Passed | 11/22/24 pass | |
11/22/2024 | COT - RSPL - Yard Water Line | Passed | 11/22/24 pass | |
12/03/2024 | COT - RSEL - Electrical Underground | Passed | Conduit not in place. 12/2/2024 12/3/24: corrections made. |
|
12/26/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | 12/26/24 pass | |
12/26/2024 | COT - RSBU - Roof Nailing | Passed | 12/26/24 pass | |
02/06/2025 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | 2/6/25 pass | |
02/06/2025 | RSBU - Building Progress | Passed | ||
02/13/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 2/13/25 pass | |
02/13/2025 | COT - RSPL - Gas Pressure Test | Passed | 2/13/25 pass |