Permit Details

Status:
Complete
Type:
Model Building Permit
Address:
9652 E HARKES DR
Address NEW:
9652 E HARKES DR
Apply Date:
04/22/2024
Applicant:
Brianna Quiroz
Description:
Eisenhower Model Plan La Escalera

Permit Reviews

Permit Number - TC-MDP-1023-01702
Permit Status: Complete
Permit Description: Eisenhower Model Plan La Escalera
Start Date Submittal Complete Date Status  
04/26/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 05/01/2024 APPROVED Review Details
02/24/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/26/2025 REQUIRES RESUBMIT Review Details
03/05/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 03/10/2025 APPROVED Review Details

Conditions

Permit Number - TC-MDP-1023-01702
Permit Status: Complete
Permit Description: Eisenhower Model Plan La Escalera
Date Description Comments
05/01/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
04/30/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/30/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
01/20/2023 Post-Tension Inspection Report is required.
04/30/2024 Post-Tension Inspection Report is required.
10/25/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
02/25/2025 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
01/20/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
04/30/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-1023-01702
Permite Description: Eisenhower Model Plan La Escalera
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
06/07/2024 COT - RSPL - Yard Water Line N/A Re-inspection required 6/7/24: pressure gauge not working
11/12/2024 COT - BULD - SWG Clearance N/A Not Applicable 11-12-24, not applicable-homes do not contain gas.
11/12/2024 COT - RSPL - Gas Pressure Test N/A Not Applicable 11-12-24, not applicable-homes do not contain gas.
03/11/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required 3-11-25, letter submitted from Austin Electric has not yet been reviewed nor approved by the city.
03/11/2025 COT - RSME - Mechanical Final N/A Re-inspection required 3-11-25, connect and anchor down dishwasher.
03/11/2025 COT - RSPL - Plumbing Final N/A Re-inspection required 3-11-25, connect and anchor down dishwasher, bad light switch on stairs, paint all exterior plastic.
03/11/2025 COT - RSEL - Electrical Final N/A Re-inspection required 3-11-25, connect and anchor down dishwasher, bad light switch on stairs, paint all exterior plastic.
03/11/2025 RSBU - Building Final N/A Re-inspection required 3-11-25, connect and anchor down dishwasher, bad light switch on stairs, paint all exterior plastic.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-1023-01702
Permit Description: Eisenhower Model Plan La Escalera
Total Completed Inspections - 20
Date Description Inspector Results Comments
06/07/2024 COT - RSPL - Backwater Valve Passed
06/07/2024 COT - RSPL - Rough Soil Passed
06/14/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
06/14/2024 COT - RSBU - Preslab Passed
06/14/2024 COT - RSEL - Electrical Underground Passed
06/14/2024 COT - RSEL - Grounding/Bonding Passed
06/14/2024 COT - RSPL - Yard Water Line Passed
08/08/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
08/08/2024 COT - RSBU - Roof Nailing Passed
10/16/2024 COT - RSPL - Sewer Passed DWV Pipes are connected to the main sewer line and under water pressure test with no leaks.
12/09/2024 COT - RSBU - Interior Shear Bracing Passed 12-9-24, interior shear bracing inspection verified as per approved plans. Okay to tape & texture drywall.
01/22/2025 BULD - Electrical Clearance Passed 1/22/25 approval for TEP ECO
03/11/2025 COT - RSEL - Outdoor Lighting Passed 3-11-25, approved
03/11/2025 RSBU - Building Progress Passed
03/12/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 3/12/25 letter needed for cfo
03/12/2025 COT - RSME - Mechanical Final Passed 3/12/25 corrections made
03/12/2025 COT - RSPL - Plumbing Final Passed 3/12/25 corrections made
03/12/2025 ENGR Engineering Final Passed
03/13/2025 COT - RSEL - Electrical Final Passed
03/13/2025 RSBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
LOT 45 SIC-2025-03-04_V2.PDF DOCUMENTS VIEW
USE - PATTISON SOILS REPORT 1.25.2022_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
PHASE 1 LOT 45 PLOT PLAN_V1.PDF DOCUMENTS VIEW
PHASE 1A LOT 45 SIC-2024-04-22_V1.PDF DOCUMENTS VIEW