Permit: TC-MDP-0924-01132
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6092 E BLACK CAVIAR PL
Address NEW:
6092 E BLACK CAVIAR PL
Apply Date:
09/26/2024
Applicant:
Helen Ormsby
Description:
Blackhawk H30M Model Plan (Model Master Plan TC-MDP-0823-01436)
Permit Reviews
Permit Number - TC-MDP-0924-01132
Permit Status: Inspections complete
Permit Description: Blackhawk H30M Model Plan (Model Master Plan TC-MDP-0823-01436)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/27/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 10/02/2024 | APPROVED |
| 10/08/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 10/10/2025 | APPROVED |
| 09/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/25/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-MDP-0924-01132
Permit Status: Inspections complete
Permit Description: Blackhawk H30M Model Plan (Model Master Plan TC-MDP-0823-01436)
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/26/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
Conditions
Permit Number - TC-MDP-0924-01132
Permit Status: Inspections complete
Permit Description: Blackhawk H30M Model Plan (Model Master Plan TC-MDP-0823-01436)
| Date | Description | Comments |
|---|---|---|
| 10/01/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 10/01/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 09/26/2024 | Post-Tension Inspection Report is required. | |
| 09/26/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 10/01/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 10/01/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0924-01132
Permite Description: Blackhawk H30M Model Plan (Model Master Plan TC-MDP-0823-01436)
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/23/2025 | COT - RSPL - Rough Soil | N/A | Re-inspection required | Plumbing not per plan. Stack needs to be topped off. 6/23/2025 |
| 06/23/2025 | COT - RSPL - Sewer | N/A | Re-inspection required | Plumbing not per plan. Stack needs to be topped off. 6/23/2025 |
| 09/08/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Partial Pass | 9-8-25: partial pass replace kitchen shear wall due to too many over penetrations-structural integrity has been compromised. Shear wall to be checked at intermediates-okay to continue with construction at progress areas. |
| 09/16/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 9.16.2025 In garage corner pop out needs foam at penetration, secure electrical line and add nail plate in garage, secure electrical lines at panel, update panel schedule and plan states conductor material is copper and not copper-clad - plan calls for 15A circuit but code E3703.5 requires 20A in garage (wire is white, should be yellow for cu clad 20A), DWV has leak in bathroom and same 3"line requires brace support, gas pressure test reading 13psi but requires 15psi, add staples at south shear wall and foam top plate as marked. Next inspector needs complete walkthrough in 1 & 2 floors. STOPPED INSPECTION, MORE ITEMS MAY BE FOUND. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0924-01132
Permit Description: Blackhawk H30M Model Plan (Model Master Plan TC-MDP-0823-01436)
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/23/2025 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading is required. 6/23/2025 | |
| 06/25/2025 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading is required. 6/25/2025 | |
| 06/25/2025 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading is required. 6/25/2025 | |
| 08/11/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 8.11.25 Footer depths verified Rebar verified Pipes wrapped Clearances verified |
|
| 08/11/2025 | COT - RSBU - Preslab | Passed | 8.11.25 Footer depths verified Rebar verified Pipes wrapped Clearances verified |
|
| 08/11/2025 | COT - RSEL - Electrical Underground | Passed | 8.11.25 Footer depths verified Rebar verified Pipes wrapped Clearances verified |
|
| 09/04/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 09/09/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 9.9.25 Corrections made |
|
| 09/16/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 09/18/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 9.18.2025 Corrections made to prior inspection on 9.16.2025 and walked second floor, added foam to penetrations and holes at sill plate. Shower in second floor holding water added. Staples added to main panel runs. |
|
| 09/19/2025 | COT - RSPL - Gas Pressure Test | Passed | 9-19-25: approved. | |
| 09/29/2025 | COT - RSBU - Interior Shear Bracing | Passed | approved | |
| 10/01/2025 | BULD - Electrical Clearance | Passed | 10/1/25: ECO TEP CLEARANCE | |
| 10/30/2025 | COT - BULD - SWG Clearance | Passed | 10.30.2025 Clearance for Southwest Gas. |
|
| 11/14/2025 | COT - RSEL - Electrical Final | Passed | ||
| 11/14/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 11/14/2025 | COT - RSME - Mechanical Final | Passed | ||
| 11/14/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 11/14/2025 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 11/14/2025 | RSBU - Building Final | Passed | ||
| 11/14/2025 | RSBU - Building Progress | Passed |