Permit: TC-MDP-0924-01052
Permit Details
Apply Date:
09/19/2024
Applicant:
Ana Chavez
Description:
duplex model plan (Model master plan TC-MDP-0824-00864)
Permit Reviews
Permit Number - TC-MDP-0924-01052
Permit Status: Complete
Permit Description: duplex model plan (Model master plan TC-MDP-0824-00864)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2025 | RESTAMP - RESIDENTIAL v.1 | 01/19/2025 | APPROVED |
| 10/01/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 10/10/2024 | REQUIRES RESUBMIT |
| 09/24/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 09/24/2024 | REQUIRES RESUBMIT |
| 12/19/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 | 01/09/2025 | REQUIRES RESUBMIT |
| 01/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/09/2025 | APPROVED |
| 01/13/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 | 01/14/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0924-01052
Permit Status: Complete
Permit Description: duplex model plan (Model master plan TC-MDP-0824-00864)
| Date | Description | Comments |
|---|---|---|
| 01/13/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 02/07/2025 | An intermediate Elevation Certificate is required PRIOR TO GRADING and/or PRE-SLAB INSPECTION. | |
| 02/07/2025 | Submission of the final Elevation Certificate and completion of the Floodplain Use Permit is required PRIOR TO FINALING this permit. | |
| 09/19/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0924-01052
Permite Description: duplex model plan (Model master plan TC-MDP-0824-00864)
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/28/2025 | COT - RSBU - Preslab and floodplain | N/A | Partial Pass | 1/28/25: floodplain certification has not been approved. Pending approval. Reinforcement per plan. |
| 04/17/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | 4-17-25, not applicable |
| 04/17/2025 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | 4-17-25, not applicable |
| 02/07/2025 | COT - RSBU - Interior Shear Bracing | N/A | Partial Pass | 2/7/25 we will need to see the gypsum board before taping. Partial |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0924-01052
Permit Description: duplex model plan (Model master plan TC-MDP-0824-00864)
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/22/2025 | COT - RSPL - Rough Soil | Passed | Passed 1/22/25 ok to backfill | |
| 01/28/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 1/28/25: floodplain certification has not been approved. Pending approval. Reinforcement per plan. | |
| 01/31/2025 | COT - RSBU - Preslab and floodplain | Passed | 1/31/25: approved by J. Garcia | |
| 02/07/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 2/7/25 pass | |
| 02/07/2025 | COT - RSBU - Roof Nailing | Passed | 2/7/25 pass | |
| 02/14/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Ok to insulate and cover walls. | |
| 02/14/2025 | COT - RSPL - Yard Water Line | Passed | Ok to cover progress areas. | |
| 02/26/2025 | BULD - Electrical Clearance | Passed | Passed 2/26/25 ready for temp power CLEARANCE ECO | |
| 04/16/2025 | COT - RSPL - Sewer | Passed | 4-16-25, approximately 80' of Schedule 40-4" sewer line/connection verified under test and per plans-Okay to backfill. | |
| 04/17/2025 | COT - RSEL - Grounding/Bonding | Passed | 4-17-25, approved. | |
| 04/17/2025 | COT - RSEL - Electrical Underground | Passed | 4-17-25, previously inspected and approved. | |
| 04/17/2025 | COT - RSEL - Outdoor Lighting | Passed | 4-17-25, approved. | |
| 04/17/2025 | RSBU - Building Progress | Passed | 4-17-25, approved. | |
| 04/18/2025 | COT - RSEL - Electrical Final | Passed | 4-18-25, mechanical, electrical, plumbing, outdoor lighting approved. | |
| 04/18/2025 | COT - RSME - Mechanical Final | Passed | 4-18-25, mechanical, electrical, plumbing, outdoor lighting approved. | |
| 04/18/2025 | COT - RSPL - Plumbing Final | Passed | 4-18-25, mechanical, electrical, plumbing, outdoor lighting approved. | |
| 04/21/2025 | COT - RSBU - Interior Shear Bracing | Passed | 4/21/2025 letter has been uploaded and under review. | |
| 04/22/2025 | RSBU - Building Final | Passed | ||
| 04/22/2025 | ENGR Engineering Final | Passed |