Permit Reviews
Permit Number - TC-MDP-0825-00446
Permit Status: Complete
Permit Description: Residential SFR Model Plan (Model master plan TC-MDP-0325-00178)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/31/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 11/13/2025 | REQUIRES RESUBMIT |
| 01/20/2026 | ADMINISTRATIVE v.2 | 01/20/2026 | APPROVED |
| 01/13/2026 | ADMINISTRATIVE v.1 | 01/13/2026 | REQUIRES RESUBMIT |
| 06/02/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/02/2026 | APPROVED |
| 01/02/2026 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 01/13/2026 | APPROVED |
Conditions
Permit Number - TC-MDP-0825-00446
Permit Status: Complete
Permit Description: Residential SFR Model Plan (Model master plan TC-MDP-0325-00178)
| Date | Description | Comments |
|---|---|---|
| 01/12/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. | |
| 08/15/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 08/15/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 08/15/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 01/12/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0825-00446
Permite Description: Residential SFR Model Plan (Model master plan TC-MDP-0325-00178)
Total Outstanding Inspections - 10
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/10/2026 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Re-inspection required | 3-10-26: provide a 1 1/2" clearance between DWV & forms, install chairs/blocks throughout pad, footing depth not per plans-a few areas at 21", reinforcement at pad is not per plans-should be #3 rebar @ 24' o.c., add reinforcement, compact pad -noted puddle of water along with water in footing. |
| 03/10/2026 | COT - RSBU - Preslab | N/A | Re-inspection required | 3-10-26: provide a 1 1/2" clearance between DWV & forms, install chairs/blocks throughout pad, footing depth not per plans-a few areas at 21", reinforcement at pad is not per plans-should be #3 rebar @ 24' o.c., add reinforcement, compact pad -noted puddle of water along with water in footing. |
| 03/26/2026 | COT - RSBU - Roof Nailing | N/A | Not Ready | Provide ladder prior to next inspection. 3/26/2026 |
| 03/26/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Not Ready | |
| 03/26/2026 | COT - RSBU - Interior Shear Bracing | N/A | Partial Pass | Partial pass. 1st fire wall approved. 3/26/2026 |
| 05/29/2026 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 05/14/2026 | ENGR Engineering Final | N/A | Not Ready | |
| 06/15/2026 | COT - RSEL - Electrical Final | N/A | Not Ready | |
| 06/15/2026 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
| 06/15/2026 | RSBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0825-00446
Permit Description: Residential SFR Model Plan (Model master plan TC-MDP-0325-00178)
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/02/2026 | COT - RSPL - Sewer | Passed | 3” sewer line connected to main sewer line. Ok to cover progress areas. | |
| 03/27/2026 | COT - RSBU - Roof Nailing | Passed | ||
| 03/27/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | All corrections were made. No additional items were found. 3/27/2026 | |
| 04/24/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 05/05/2026 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 05/05/2026 | COT - RSPL - Yard Water Line | Passed | ||
| 05/11/2026 | BULD - Electrical Clearance | Passed | 05/11/2026 Clearance TEP ECO. Duplex unit 1 & 2. |
|
| 05/29/2026 | COT - RSPL - Rough Soil | Passed | ||
| 05/29/2026 | COT - RSEL - Grounding/Bonding | Passed | 05/29/2026 Verified two ground rods tied into main service panel. |
|
| 06/11/2026 | COT - RSEL - Outdoor Lighting | Passed | 6-11-26: outdoor lighting approved. | |
| 06/11/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 06/15/2026 | COT - RSME - Mechanical Final | Passed | ||
| 06/16/2026 | COT - RSEL - Electrical Final | Passed | 06/16/2026 Corrections made to condensate and whips, verified painted exposed plastic. Verified AFCI breakers for branch circuits, insulated hot water line. Panel schedule labeled. |
|
| 06/16/2026 | COT - RSPL - Plumbing Final | Passed | 06/16/2026 Corrections made to condensate and whips, verified painted exposed plastic. |
|
| 06/16/2026 | RSBU - Building Final | Passed | 06/16/2026 Corrections made to condensate and whips, verified painted exposed plastic. Verified AFCI breakers for branch circuits, insulated hot water line. Panel schedule labeled. |