Permit: TC-MDP-0824-00893
Permit Details
Apply Date:
06/11/2025
Applicant:
Ana Chavez
Description:
New Residential Model De La Cruz-(Model master plan TC-MDP-0623-01107)
Permit Reviews
Permit Number - TC-MDP-0824-00893
Permit Status: Complete
Permit Description: New Residential Model De La Cruz-(Model master plan TC-MDP-0623-01107)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/11/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 08/25/2025 | REQUIRES RESUBMIT |
| 12/12/2025 | SITE FROM MODEL TEMPLATE INFILL BUILDERS REVISION v.1 | 12/16/2025 | IN REVIEW |
| 10/17/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 | 10/20/2025 | APPROVED |
| 09/05/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 | 09/23/2025 | REQUIRES RESUBMIT |
| 01/29/2026 | SITE FROM MODEL TEMPLATE INFILL BUILDERS REVISION v.2 | N/A | IN REVIEW |
| 11/10/2025 | RESTAMP - RESIDENTIAL v.1 | 11/12/2025 | APPROVED |
| 11/04/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 11/10/2025 | APPROVED |
| 06/17/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 07/29/2025 | REQUIRES RESUBMIT |
| 10/20/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 10/30/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0824-00893
Permit Status: Complete
Permit Description: New Residential Model De La Cruz-(Model master plan TC-MDP-0623-01107)
| Date | Description | Comments |
|---|---|---|
| 06/17/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 08/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 08/23/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0824-00893
Permite Description: New Residential Model De La Cruz-(Model master plan TC-MDP-0623-01107)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/23/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 03/23/2026 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0824-00893
Permit Description: New Residential Model De La Cruz-(Model master plan TC-MDP-0623-01107)
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2025 | COT - RSPL - Rough Soil | Passed | 11.19.25 System is installed per plans and under water test. APPROVED PROCEED |
|
| 11/24/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Rebar in footings and rebar ufer in place. Ok to place concrete when footings dry-out. | |
| 11/24/2025 | COT - RSBU - Preslab | Passed | Do not place concrete until slab is dry and termite treated. | |
| 12/08/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Passed 12/8/25 | |
| 12/08/2025 | COT - RSBU - Interior Shear Bracing | Passed | Passed 12/8/25 | |
| 12/08/2025 | COT - RSBU - Roof Nailing | Passed | Passed 12/8/25 | |
| 12/12/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 01/06/2026 | BULD - Electrical Clearance | Passed | Ready for temp power CLEARANCE ECO | |
| 01/29/2026 | COT - RSPL - Yard Water Line | Passed | Waiting for Tucson Water to set meter. | |
| 02/18/2026 | COT - RSPL - Sewer | Passed | Main sewer line at 7’, Ok to tap and cover progress area. Site work to be completed this date. | |
| 03/23/2026 | COT - RSEL - Electrical Final | Passed | ||
| 03/23/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 03/23/2026 | COT - RSEL - Grounding/Bonding | Passed | ||
| 03/23/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 03/23/2026 | COT - RSME - Mechanical Final | Passed | ||
| 03/23/2026 | COT - RSPL - Plumbing Final | Passed | ||
| 03/23/2026 | RSBU - Building Final | Passed | ||
| 03/23/2026 | RSBU - Building Progress | Passed | ||
| 03/27/2026 | ENGR Engineering Final | Passed | Accessible route OK. Contractor built gate 14 feet wide gate for driveway on alley side of property. Confirmed with Engineering Associate Cory Hines that this was acceptable and per his prior approval. |