Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
08/23/2023
Applicant:
Amy Stokes, Operations Accountant
Description:
SFR RKM45R T21-M0093 (REVISION Delta 4)

Permit Reviews

Permit Number - TC-MDP-0823-01450
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Start Date Submittal Complete Date Status  
09/26/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/27/2023 APPROVED Review Details
08/23/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 08/28/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0823-01450
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Outstanding Activity Conditions - 6
Date Name
08/23/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
08/23/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/23/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
08/23/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
08/28/2023 Post-Tension Inspection Report is required.
08/28/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0823-01450
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Date Description Comments
09/27/2023 ISSUED WITH PDEQ CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PRIVATE SEWER #P21SD0033 IS ISSUED A DISCHARGE AUTHORIZATION BY PDEQ
08/23/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01450
Permite Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
07/31/2024 COT - RSEL - Electrical Final N/A Re-inspection required 7/31/24: irrigation breaker not installed, "for future solar" required at panel,secure electrical whip at irrigation, fencing not installed at time of inspection, 6" min from weep screed to grade , UV tape hose bib, gray water clean outs must be cut to grade and capped, Pad at A/C condenser needs 3" clearance form grade on all sides, high loop at dishwasher must be installed, no attic access, Tempered glass not installed at master shower, garage door rating tag has been painted over,
07/31/2024 COT - RSEL - Outdoor Lighting N/A Re-inspection required 7/31/24: irrigation breaker not installed, "for future solar" required at panel,secure electrical whip at irrigation, fencing not installed at time of inspection, 6" min from weep screed to grade , UV tape hose bib, gray water clean outs must be cut to grade and capped, Pad at A/C condenser needs 3" clearance form grade on all sides, high loop at dishwasher must be installed, no attic access, Tempered glass not installed at master shower, garage door rating tag has been painted over,
07/31/2024 COT - RSME - Mechanical Final N/A Re-inspection required 7/31/24: irrigation breaker not installed, "for future solar" required at panel,secure electrical whip at irrigation, fencing not installed at time of inspection, 6" min from weep screed to grade , UV tape hose bib, gray water clean outs must be cut to grade and capped, Pad at A/C condenser needs 3" clearance form grade on all sides, high loop at dishwasher must be installed, no attic access, Tempered glass not installed at master shower, garage door rating tag has been painted over,
07/31/2024 COT - RSPL - Plumbing Final N/A Re-inspection required 7/31/24: irrigation breaker not installed, "for future solar" required at panel,secure electrical whip at irrigation, fencing not installed at time of inspection, 6" min from weep screed to grade , UV tape hose bib, gray water clean outs must be cut to grade and capped, Pad at A/C condenser needs 3" clearance form grade on all sides, high loop at dishwasher must be installed, no attic access, Tempered glass not installed at master shower, garage door rating tag has been painted over,
07/31/2024 RSBU - Building Final N/A Re-inspection required 7/31/24: irrigation breaker not installed, "for future solar" required at panel,secure electrical whip at irrigation, fencing not installed at time of inspection, 6" min from weep screed to grade , UV tape hose bib, gray water clean outs must be cut to grade and capped, Pad at A/C condenser needs 3" clearance form grade on all sides, high loop at dishwasher must be installed, no attic access, Tempered glass not installed at master shower, garage door rating tag has been painted over,
07/31/2024 RSBU - Building Progress N/A Re-inspection required 7/31/24: irrigation breaker not installed, "for future solar" required at panel,secure electrical whip at irrigation, fencing not installed at time of inspection, 6" min from weep screed to grade , UV tape hose bib, gray water clean outs must be cut to grade and capped, Pad at A/C condenser needs 3" clearance form grade on all sides, high loop at dishwasher must be installed, no attic access, Tempered glass not installed at master shower, garage door rating tag has been painted over,

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01450
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Completed Inspections - 21
Date Description Inspector Results Comments
03/20/2024 COT - RSPL - Yard Water Line Passed
03/20/2024 COT - RSPL - Sewer Passed
03/20/2024 COT - RSPL - Rough Soil Passed
04/02/2024 COT - RSEL - Electrical Underground Passed
04/03/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 4/3/24: Excess water has been removed from trenches, Masa clips have been added to form, and debris has been removed from trenches and slab area. Okay to pour concrete when ready.
04/03/2024 COT - RSBU - Preslab Passed 4/3/24: Excess water has been removed from trenches, Masa clips have been added to form, and debris has been removed from trenches and slab area. Okay to pour concrete when ready.
04/03/2024 COT - RSEL - Grounding/Bonding Passed 4/3/24: Excess water has been removed from trenches, Masa clips have been added to form, and debris has been removed from trenches and slab area. Okay to pour concrete when ready.
04/18/2024 COT - RSBU - Roof Nailing Passed
04/24/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 4/24/24: RSP clip has been added to east side of house, hurricane ties have been properly nailed on interior walls, and shear sheathing is properly secured to studs. Okay to proceed with window and door installation.
05/15/2024 BULD - Electrical Clearance Passed TEP ECO
05/15/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/15/2024 COT - RSPL - Gas Pressure Test Passed
06/06/2024 COT - RSBU - Interior Shear Bracing Passed
07/25/2024 COT - BULD - SWG Clearance Passed SWG for meter only
07/31/2024 ENGR Engineering Final Passed Just a note, screen fence on left side not completed
08/07/2024 COT - RSEL - Electrical Final Passed 8/7/24: All items from last inspection have been corrected or cleaned. Mechanical, electrical, and plumbing fixtures are installed and properly working. Electrical panel is properly labeled with correct breaker sizes installed. Okay to issue Certificate of Occupancy once Fire and engineering complete their inspections.
08/07/2024 COT - RSEL - Outdoor Lighting Passed 8/7/24: All items from last inspection have been corrected or cleaned. Mechanical, electrical, and plumbing fixtures are installed and properly working. Electrical panel is properly labeled with correct breaker sizes installed. Okay to issue Certificate of Occupancy once Fire and engineering complete their inspections.
08/07/2024 COT - RSME - Mechanical Final Passed 8/7/24: All items from last inspection have been corrected or cleaned. Mechanical, electrical, and plumbing fixtures are installed and properly working. Electrical panel is properly labeled with correct breaker sizes installed. Okay to issue Certificate of Occupancy once Fire and engineering complete their inspections.
08/07/2024 COT - RSPL - Plumbing Final Passed 8/7/24: All items from last inspection have been corrected or cleaned. Mechanical, electrical, and plumbing fixtures are installed and properly working. Electrical panel is properly labeled with correct breaker sizes installed. Okay to issue Certificate of Occupancy once Fire and engineering complete their inspections.
08/07/2024 RSBU - Building Final Passed 8/7/24: All items from last inspection have been corrected or cleaned. Mechanical, electrical, and plumbing fixtures are installed and properly working. Electrical panel is properly labeled with correct breaker sizes installed. Okay to issue Certificate of Occupancy once Fire and engineering complete their inspections.
08/07/2024 RSBU - Building Progress Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT-2023-08-23_V1.PDF DOCUMENTS VIEW