Permit: TC-MDP-0724-00820
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
4643 S VERDIN VALLEY DR
Address NEW:
4643 S VERDIN VALLEY DR
Apply Date:
08/13/2024
Applicant:
Celina Rodriguez
Description:
Bella Tierra Phase 3 1745-130
Permit Reviews
Permit Number - TC-MDP-0724-00820
Permit Status: Inspections complete
Permit Description: Bella Tierra Phase 3 1745-130
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/19/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 08/23/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0724-00820
Permit Status: Inspections complete
Permit Description: Bella Tierra Phase 3 1745-130
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 07/25/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 08/21/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 08/21/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 08/21/2024 | Post-Tension Inspection Report is required. |
| 08/21/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0724-00820
Permit Status: Inspections complete
Permit Description: Bella Tierra Phase 3 1745-130
| Date | Description | Comments |
|---|---|---|
| 07/25/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0724-00820
Permite Description: Bella Tierra Phase 3 1745-130
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/04/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Re-inspection required | 10/4/24: Anchor bolts required throughout exterior perimeter wall and interior shear walls (spacing is greater than 23" o.c at shear walls 11 and 3x3 plates required) (spacing of anchor bolts greater than 6' o.c) (anchor bolts required 12" from edge of sill plate) (sill plates larger than 12" require 2 anchor bolts), garage opening requires 3king studs, shear wall fasteners not per schedule. STOPPED INSPECTION MORE ITEMS MAY BE ADDED. |
| 10/04/2024 | COT - RSBU - Roof Nailing | N/A | Re-inspection required | 10/4/24: Anchor bolts required throughout exterior perimeter wall and interior shear walls (spacing is greater than 23" o.c at shear walls 11 and 3x3 plates required) (spacing of anchor bolts greater than 6' o.c) (anchor bolts required 12" from edge of sill plate) (sill plates larger than 12" require 2 anchor bolts), garage opening requires 3king studs, shear wall fasteners not per schedule. STOPPED INSPECTION MORE ITEMS MAY BE ADDED. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0724-00820
Permit Description: Bella Tierra Phase 3 1745-130
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/11/2024 | COT - RSPL - Sewer | Passed | Under plumbing is installed and connected to main sewer line. Backwater valve is installed between two clean outs. Entire system is under a water test with no leaks. | |
| 09/11/2024 | COT - RSPL - Backwater Valve | Passed | Under plumbing is installed and connected to main sewer line. Backwater valve is installed between two clean outs. Entire system is under a water test with no leaks. | |
| 09/11/2024 | COT - RSPL - Rough Soil | Passed | Under plumbing is installed and connected to main sewer line. Backwater valve is installed between two clean outs. Entire system is under a water test with no leaks. | |
| 09/18/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 09/18/2024 | COT - RSBU - Preslab | Passed | ||
| 09/18/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 09/18/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 10/09/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 10/9/24: Noted items above have been corrected. Okay to proceed with rough-in. | |
| 10/09/2024 | COT - RSBU - Roof Nailing | Passed | 10/9/24: Noted items above have been corrected. Okay to proceed with rough-in. | |
| 11/08/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | M, P, & E rough-in is complete. Okay to proceed with installation of insulation and drywall. | |
| 11/08/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is holding 15psi of air pressure with no leaks. Okay to proceed. | |
| 11/22/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 11/22/2024 | COT - RSPL - Yard Water Line | Passed | Water line is connected to meter and under street pressure with no leaks. | |
| 12/20/2024 | BULD - Electrical Clearance | Passed | 12/20/24 ELECTRICAL CLEARANCE ECO | |
| 01/17/2025 | COT - BULD - SWG Clearance | Passed | SWG Clearance issued for 4643 S. Verdin Valley Drive. All valves are installed at gas appliance locations. | |
| 02/12/2025 | COT - RSEL - Electrical Final | Passed | 2/12/24 | |
| 02/12/2025 | COT - RSEL - Outdoor Lighting | Passed | 2/12/25 pass | |
| 02/12/2025 | COT - RSME - Mechanical Final | Passed | 2/12/25 pass | |
| 02/12/2025 | COT - RSPL - Plumbing Final | Passed | 2/12/24 pass | |
| 02/12/2025 | ENGR Engineering Final | Passed | ||
| 02/12/2025 | RSBU - Building Final | Passed | 2/12/25 pass | |
| 02/12/2025 | RSBU - Building Progress | Passed |