Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0724-00794
Permit Details
Apply Date:
08/16/2024
Applicant:
Stephanie Bebee
Description:
PV 1371SFR
Permit Reviews
Permit Number - TC-MDP-0724-00794
Permit Status: Issued
Permit Description: PV 1371SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/17/2024 | APPROVED |
09/24/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.2 | 10/01/2024 | APPROVED |
10/01/2024 | RESTAMP - RESIDENTIAL v.1 | 10/04/2024 | IN REVIEW |
08/22/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/28/2024 | REQUIRES RESUBMIT |
10/04/2024 | RESTAMP - RESIDENTIAL v.2 | 10/04/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0724-00794
Permit Status: Issued
Permit Description: PV 1371SFR
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
08/26/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
08/26/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
08/26/2024 | Post-Tension Inspection Report is required. |
Conditions
Permit Number - TC-MDP-0724-00794
Permit Status: Issued
Permit Description: PV 1371SFR
Date | Description | Comments |
---|---|---|
07/12/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
07/12/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
10/04/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0724-00794
Permit Description: PV 1371SFR
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/21/2024 | COT - RSPL - Backwater Valve | Passed | 1021/24 OK TO BACK FILL SHADING REQUIRED. | |
10/21/2024 | COT - RSPL - Yard Water Line | Passed | 1021/24 OK TO BACK FILL SHADING REQUIRED. | |
10/21/2024 | COT - RSPL - Sewer | Passed | 1021/24 OK TO BACK FILL SHADING REQUIRED. | |
10/21/2024 | COT - RSPL - Rough Soil | Passed | 1021/24 OK TO BACK FILL SHADING REQUIRED. | |
10/25/2024 | COT - RSEL - Electrical Underground | Passed | ||
10/25/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
10/28/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Corrections made 10/28/24 | |
10/28/2024 | COT - RSBU - Preslab | Passed | Corrections made 10/28/24 | |
11/26/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Ok to cover exterior walls | |
11/26/2024 | COT - RSBU - Roof Nailing | Passed | OK to dry-in roof system |