Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Address:
2667 S AYALA ST
Address NEW:
2667 S AYALA ST
Apply Date:
07/18/2024
Applicant:
Mark Alteri
Description:
PV 1882 SFR

Permit Reviews

Permit Number - TC-MDP-0724-00789
Permit Status: Complete
Permit Description: PV 1882 SFR
Start Date Submittal Complete Date Status  
12/16/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/17/2024 APPROVED Review Details
07/22/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 07/30/2024 REQUIRES RESUBMIT Review Details
11/15/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/18/2024 APPROVED Review Details
08/01/2024 SITE FROM MODEL PERMIT - PRODUCTION v.2 08/07/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0724-00789
Permit Status: Complete
Permit Description: PV 1882 SFR
Date Description Comments
08/07/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
08/07/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
08/07/2024 Post-Tension Inspection Report is required.
07/12/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/12/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
07/30/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0724-00789
Permite Description: PV 1882 SFR
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
12/23/2024 COT - RSBU - Interior Shear Bracing N/A Partial Pass 12/22/24 shear wall at second floor opposite closet not to schedule, and missing screws at bedroom by patio wall.
12/02/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Not Ready
04/10/2025 COT - RSEL - Electrical Final N/A Re-inspection required 4/10/25: Knock-outs at main panel must be sealed, liquid tight at irrigation system must be secured, 1/2" conduit at irrigation box must be secured, exposed in treated wood must be treated at final inspection, hose bibs must be insulated, hot water lines at garage must be insulated, post tension tag required at exterior hose bib, garage must be self closing and rated, secure gas line under range, high loop at dishwasher must be properly secured, properly secure electrical whip for oven and install faceplate, GFCI required at bathrooms, plumbing fixtures not installed. Exterior plastic piping must be coated for UV protection, all faceplates at boxes must be properly installed, WR receptacles required on exterior of home . STOPPED INSPECTION MORE ITEMS MAY BE ADDED (second floor was not inspected)
04/10/2025 COT - RSEL - Outdoor Lighting N/A Re-inspection required 4/10/25: Knock-outs at main panel must be sealed, liquid tight at irrigation system must be secured, 1/2" conduit at irrigation box must be secured, exposed in treated wood must be treated at final inspection, hose bibs must be insulated, hot water lines at garage must be insulated, post tension tag required at exterior hose bib, garage must be self closing and rated, secure gas line under range, high loop at dishwasher must be properly secured, properly secure electrical whip for oven and install faceplate, GFCI required at bathrooms, plumbing fixtures not installed. Exterior plastic piping must be coated for UV protection, all faceplates at boxes must be properly installed, WR receptacles required on exterior of home . STOPPED INSPECTION MORE ITEMS MAY BE ADDED (second floor was not inspected)
04/10/2025 COT - RSME - Mechanical Final N/A Re-inspection required 4/10/25: Knock-outs at main panel must be sealed, liquid tight at irrigation system must be secured, 1/2" conduit at irrigation box must be secured, exposed in treated wood must be treated at final inspection, hose bibs must be insulated, hot water lines at garage must be insulated, post tension tag required at exterior hose bib, garage must be self closing and rated, secure gas line under range, high loop at dishwasher must be properly secured, properly secure electrical whip for oven and install faceplate, GFCI required at bathrooms, plumbing fixtures not installed. Exterior plastic piping must be coated for UV protection, all faceplates at boxes must be properly installed, WR receptacles required on exterior of home . STOPPED INSPECTION MORE ITEMS MAY BE ADDED (second floor was not inspected)
04/10/2025 COT - RSPL - Plumbing Final N/A Re-inspection required 4/10/25: Knock-outs at main panel must be sealed, liquid tight at irrigation system must be secured, 1/2" conduit at irrigation box must be secured, exposed in treated wood must be treated at final inspection, hose bibs must be insulated, hot water lines at garage must be insulated, post tension tag required at exterior hose bib, garage must be self closing and rated, secure gas line under range, high loop at dishwasher must be properly secured, properly secure electrical whip for oven and install faceplate, GFCI required at bathrooms, plumbing fixtures not installed. Exterior plastic piping must be coated for UV protection, all faceplates at boxes must be properly installed, WR receptacles required on exterior of home . STOPPED INSPECTION MORE ITEMS MAY BE ADDED (second floor was not inspected)
04/10/2025 RSBU - Building Final N/A Re-inspection required 4/10/25: Knock-outs at main panel must be sealed, liquid tight at irrigation system must be secured, 1/2" conduit at irrigation box must be secured, exposed in treated wood must be treated at final inspection, hose bibs must be insulated, hot water lines at garage must be insulated, post tension tag required at exterior hose bib, garage must be self closing and rated, secure gas line under range, high loop at dishwasher must be properly secured, properly secure electrical whip for oven and install faceplate, GFCI required at bathrooms, plumbing fixtures not installed. Exterior plastic piping must be coated for UV protection, all faceplates at boxes must be properly installed, WR receptacles required on exterior of home . STOPPED INSPECTION MORE ITEMS MAY BE ADDED (second floor was not inspected)

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0724-00789
Permit Description: PV 1882 SFR
Total Completed Inspections - 22
Date Description Inspector Results Comments
08/29/2024 COT - RSPL - Backwater Valve Passed
08/30/2024 COT - RSPL - Rough Soil Passed
08/30/2024 COT - RSPL - Yard Water Line Passed
09/06/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 9/6/24: reinforcement per plan. Ok to proceed
09/06/2024 COT - RSBU - Preslab Passed 9/6/24: reinforcement per plan ok to proceed,
09/06/2024 COT - RSEL - Electrical Underground Passed 9/6/24: Electrical underground per plans
10/07/2024 COT - RSBU - Roof Nailing Passed
10/09/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 10/7/24: anchor bolts at shear-walls and exterior walls not per plan, properly fasten all anchor bolts, rsp4 not per plan, detail S2.1/14 missing on plans at interior bearing walls. Shot pins required 6" from edge of sill plate, shot pins required 36" o.c
10/9/24: corrections made. Ok to proceed
12/05/2024 COT - RSEL - Grounding/Bonding Passed
12/19/2024 COT - RSPL - Sewer Passed
12/26/2024 COT - RSBU - Interior Shear Bracing Passed 12/26/24 corrections were made. PASS
01/21/2025 BULD - Electrical Clearance Passed ECO
02/18/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
03/05/2025 COT - RSPL - Gas Pressure Test Passed 3/5/25: SWG CLEARANCE APPROVED OK FOR METER TAG
03/05/2025 COT - BULD - SWG Clearance Passed 3/5/25: SWG CLEARANCE APPROVED OK FOR METER TAG
04/10/2025 ENGR Engineering Final Passed Models are CO Ready
04/10/2025 RSBU - Building Progress Passed
04/18/2025 COT - RSEL - Electrical Final Passed 4-18-25, electrical final approved.
04/18/2025 COT - RSEL - Outdoor Lighting Passed 4-18-25, approved.
04/18/2025 COT - RSME - Mechanical Final Passed 4-18-25, mechanical final approved.
04/18/2025 COT - RSPL - Plumbing Final Passed 4-18-26, plumbing & building final approved
04/18/2025 RSBU - Building Final Passed 4-18-26, plumbing & building final approved

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
PT REPORT LOT 43 -2024-11-13_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
43 PT CERT_V1.PDF DOCUMENTS VIEW
BR 43 PP FOR PERMIT_V1.PDF DOCUMENTS VIEW