Permit: TC-MDP-0724-00783
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
7549 S CAMINO VISTA AZUL
Address NEW:
7549 S CAMINO VISTA AZUL
Apply Date:
07/08/2024
Applicant:
Craig Morczynski
Description:
SFR LENNLE4001 T22-M0045
Permit Reviews
Permit Number - TC-MDP-0724-00783
Permit Status: Inspections complete
Permit Description: SFR LENNLE4001 T22-M0045
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/15/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/15/2025 | APPROVED |
| 07/09/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 07/10/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0724-00783
Permit Status: Inspections complete
Permit Description: SFR LENNLE4001 T22-M0045
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 07/09/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 07/09/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 07/09/2024 | Post-Tension Inspection Report is required. |
| 07/09/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0724-00783
Permit Status: Inspections complete
Permit Description: SFR LENNLE4001 T22-M0045
| Date | Description | Comments |
|---|---|---|
| 07/08/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 07/13/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 07/08/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 07/13/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 07/09/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0724-00783
Permit Description: SFR LENNLE4001 T22-M0045
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2025 | COT - RSPL - Rough Soil | Passed | 2/21/25 pass | |
| 02/21/2025 | COT - RSPL - Sewer | Passed | 2/21/25 pass | |
| 02/21/2025 | COT - RSPL - Yard Water Line | Passed | 2/21/25 pass | |
| 03/06/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 03/06/2025 | COT - RSBU - Preslab | Passed | ||
| 03/06/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 03/06/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 03/24/2025 | COT - RSBU - Roof Nailing | Passed | Anchor bolts at marked locations throughout, sister damaged stud in kitchen marked, add shims in marked area at garage, per plans sliding glass doors should have 2 jack studs. STOPPED INSPECTION MORE ITEMS MAY BE ADDED | |
| 03/28/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 28 March 25 All corrections made. |
|
| 04/01/2025 | COT - RSPL - Gas Pressure Test | Passed | ||
| 04/02/2025 | BULD - Electrical Clearance | Passed | 2 April 25 TEP ELECTRICAL CLEARANCE:ECO |
|
| 04/03/2025 | RSBU - Building Progress | Passed | ||
| 04/04/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 04/16/2025 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 06/04/2025 | COT - BULD - SWG Clearance | Passed | 6.4.25 SWG clearance approved. All shut offs present, options capped, proper lines and supports present. Outdoor lines rated for use and others insulated and 10 mil tape present. Good to go. | |
| 06/16/2025 | COT - RSEL - Outdoor Lighting | Passed | 6-16-25: plumbing and outdoor lighting approved. | |
| 06/16/2025 | COT - RSPL - Plumbing Final | Passed | 6-16-25: plumbing and outdoor lighting approved. | |
| 06/16/2025 | ENGR Engineering Final | Passed | Site is clean and clear, everything is in accordance with approved plans. | |
| 06/23/2025 | COT - RSEL - Electrical Final | Passed | Approved. Corrections were made. 6/23/2025 | |
| 06/23/2025 | COT - RSME - Mechanical Final | Passed | Approved. Corrections were made. 6/23/2025 | |
| 06/23/2025 | RSBU - Building Final | Passed | Approved. Corrections were made. 6/23/2025 |