Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
7310 S DEMPSEY AV
Apply Date:
07/10/2025
Applicant:
Celina Rodriguez
Description:
KB Home 2467 (Model master plan TC-MDP-1124-01304)

Permit Reviews

Permit Number - TC-MDP-0625-00350
Permit Status: Inspections complete
Permit Description: KB Home 2467 (Model master plan TC-MDP-1124-01304)
Start Date Submittal Complete Date Status  
07/14/2025 SITE FROM MODEL PERMIT - PRODUCTION v.1 07/22/2025 REQUIRES RESUBMIT Review Details
07/24/2025 RESTAMP - RESIDENTIAL v.1 07/24/2025 APPROVED Review Details
07/24/2025 SITE FROM MODEL PERMIT - PRODUCTION v.2 07/24/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0625-00350
Permit Status: Inspections complete
Permit Description: KB Home 2467 (Model master plan TC-MDP-1124-01304)
Total Outstanding Activity Conditions - 6
Date Name
06/18/2025 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
06/18/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
07/15/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/15/2025 Post-Installed Anchor Inspection Report is required.
07/15/2025 Post-Tension Inspection Report is required.
07/15/2025 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.

Conditions

Permit Number - TC-MDP-0625-00350
Permit Status: Inspections complete
Permit Description: KB Home 2467 (Model master plan TC-MDP-1124-01304)
Date Description Comments
06/18/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
06/18/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0625-00350
Permite Description: KB Home 2467 (Model master plan TC-MDP-1124-01304)
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
08/29/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required (with fee) 8.29.2025
Nails still required on second floor on east and west bedroom shear walls, see red markings. Plans not provided on site.
09/18/2025 COT - RSBU - Interior Shear Bracing N/A Canceled 9.18.2025
Canceled by contractor.
11/13/2025 COT - BULD - SWG Clearance N/A Not Applicable
11/13/2025 COT - RSPL - Gas Pressure Test N/A Not Applicable

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0625-00350
Permit Description: KB Home 2467 (Model master plan TC-MDP-1124-01304)
Total Completed Inspections - 18
Date Description Inspector Results Comments
08/04/2025 COT - RSPL - Yard Water Line Passed 8.4.25
-plumbing verified. Tracers present. Water under pressure. 10ft head under test. Acceptable trench conditions. Proceed
08/04/2025 COT - RSPL - Sewer Passed 8.4.25
-plumbing verified. Tracers present. Water under pressure. 10ft head under test. Acceptable trench conditions. Proceed
08/04/2025 COT - RSPL - Rough Soil Passed 8.4.25
-plumbing verified. Tracers present. Water under pressure. 10ft head under test. Acceptable trench conditions. Proceed
08/11/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 8.11.25
Set backs verified
Hold downs verified
Rebar verified
Clearance verified
Various footer depths verified
Uffer verified
Pipes wrapped
Compaction verified
APPROVED OK TO POUR
08/11/2025 COT - RSBU - Preslab Passed 8.11.25
Set backs verified
Hold downs verified
Rebar verified
Clearance verified
Various footer depths verified
Uffer verified
Pipes wrapped
Compaction verified
APPROVED OK TO POUR
08/11/2025 COT - RSEL - Electrical Underground Passed 8.11.25
Set backs verified
Hold downs verified
Rebar verified
Clearance verified
Various footer depths verified
Uffer verified
Pipes wrapped
Compaction verified
APPROVED OK TO POUR
08/29/2025 COT - RSBU - Roof Nailing Passed
09/03/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
09/10/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 9.10.25
APPROVED
09/10/2025 BULD - Electrical Clearance Passed 9.10.25
APPROVED for temp power
11/13/2025 COT - RSEL - Electrical Final Passed Passed final 11/13/25
11/13/2025 COT - RSEL - Grounding/Bonding Passed Passed final 11/13/25
11/13/2025 COT - RSEL - Outdoor Lighting Passed Passed final 11/13/25
11/13/2025 COT - RSME - Mechanical Final Passed Passed final 11/13/25
11/13/2025 COT - RSPL - Plumbing Final Passed Passed final 11/13/25
11/13/2025 RSBU - Building Final Passed Passed final 11/13/25
11/13/2025 RSBU - Building Progress Passed Passed final 11/13/25
11/18/2025 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
MIRADOR POINT - LOT 1 START_V2.PDF DOCUMENTS VIEW
MP1 SIC-2025-07-10_V1.PDF DOCUMENTS VIEW