Permit: TC-MDP-0624-00715
Permit Details
Apply Date:
06/28/2024
Applicant:
Daria Hopkins
Description:
SFR 230.2380 T21-M0028
Permit Reviews
Permit Number - TC-MDP-0624-00715
Permit Status: Inspections
Permit Description: SFR 230.2380 T21-M0028
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/28/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 07/01/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0624-00715
Permit Status: Inspections
Permit Description: SFR 230.2380 T21-M0028
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/06/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0624-00715
Permit Status: Inspections
Permit Description: SFR 230.2380 T21-M0028
Date | Description | Comments |
---|---|---|
06/06/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0624-00715
Permite Description: SFR 230.2380 T21-M0028
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/22/2024 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Re-inspection required | 10/22/24: tendons with damaged sheathing must be repaired, #4 dowel at holdown 30"x30" required at garage. Site plan not provided to verify setbacks. |
10/22/2024 | COT - RSBU - Preslab | N/A | Re-inspection required | 10/22/24: tendons with damaged sheathing must be repaired, #4 dowel at holdown 30"x30" required at garage. Site plan not provided to verify setbacks. |
10/22/2024 | COT - RSEL - Grounding/Bonding | N/A | Partial Pass | 10/22/24: partial for UFER |
11/19/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 11/19/Add blocking to air ducts in laundry room and at entrance to first floor bedroom. Add fire blocking at all penetrations between floors and mechanical chase second floor. Seal all vapor barrier penetrations. Replace stud at communication box. Header in the laundry room are comprised, replace dryer vent box. Exhaust pvc not full on second floor. Nail plates throughout, I marked where you need them. Straps needed at first floor bedroom bathroom. No greywater 2" outlet at laundry room. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0624-00715
Permit Description: SFR 230.2380 T21-M0028
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/14/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading is required. 10/14/2024 | |
10/14/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading is required. 10/14/2024 | |
10/14/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading is required. 10/14/2024 | |
10/22/2024 | COT - RSEL - Electrical Underground | Passed | ||
10/24/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 10-24-24, verified setbacks together with items from previous inspection corrected. | |
10/24/2024 | COT - RSBU - Preslab | Passed | 10-24-24, listed items from previous inspection were corrected. Okay to pour. | |
10/24/2024 | COT - RSEL - Grounding/Bonding | Passed | 10-24-24, okay to pour concrete. | |
11/05/2024 | COT - RSBU - Roof Nailing | Passed | 11-5-24, all items from previous inspection have been corrected. Okay to continue construction | |
11/05/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | 11-5-24, all items from previous inspection have been corrected. Okay to continue construction | |
11/19/2024 | BULD - Electrical Clearance | Passed | 11/19/24 Clearance for TEP ECO |
|
11/19/2024 | COT - RSPL - Gas Pressure Test | Passed | 11/19/24 pass | |
11/21/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 11-21-24, listed items from previous inspection corrected. Okay to proceed with construction |