Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0523-01106
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
7355 S WILMOT RD BLDG 17
Address NEW:
7355 S WILMOT RD BLDG 17
Apply Date:
05/30/2023
Applicant:
Erin Dick
Description:
Building B three-story, 24 unit, apartment building model plans
Permit Reviews
Permit Number - TC-MDP-0523-01106
Permit Status: Complete
Permit Description: Building B three-story, 24 unit, apartment building model plans
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/29/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/30/2025 | APPROVED |
| 07/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/08/2024 | REQUIRES RESUBMIT |
| 06/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/24/2023 | APPROVED |
| 12/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/11/2024 | APPROVED |
| 05/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/27/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0523-01106
Permit Status: Complete
Permit Description: Building B three-story, 24 unit, apartment building model plans
| Date | Description | Comments |
|---|---|---|
| 09/16/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 04/21/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 04/21/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 09/16/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 04/21/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 09/16/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 04/21/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 09/16/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 05/30/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 04/21/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 09/16/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 12/11/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0523-01106
Permite Description: Building B three-story, 24 unit, apartment building model plans
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2024 | COT - LCBU - Exterior Clips/Sheathing | N/A | Partial Pass | All of 2nd floor approved. okay to proceed progress areas. 10/1/2024 |
| 05/29/2025 | COT - LCBU - Building Final | N/A | Partial Pass | 5-29-25: corrections listed from previous inspections to units in question have been corrected. Building final on all unit's from Building 17 are approved pending installation of vanity mirrors on a few units. |
| 06/03/2025 | ENGR Engineering Final | N/A | Deferred | CO Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0523-01106
Permit Description: Building B three-story, 24 unit, apartment building model plans
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/01/2023 | COT - LCPL - Rough Soil | Passed | ||
| 04/17/2024 | COT - LCPL - Yard Water Line | Passed | 4/17/24: water line under pressure ok to proceed. | |
| 04/22/2024 | COT - LCEL - Electrical Underground | Passed | ||
| 04/22/2024 | COT - LCEL - Grounding/Bonding | Passed | ||
| 04/22/2024 | COT - LCBU - Preslab | Passed | ||
| 04/22/2024 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 04/26/2024 | COT - LCPL - Sewer | Passed | 4/26/24: ok to backfill. Shading required | |
| 06/05/2024 | COT - HCPL - Yard Water Line | Passed | ||
| 07/29/2024 | COT - LCBU - Framing | Passed | ||
| 08/07/2024 | COT - BULD - SWG Clearance | Passed | ||
| 08/23/2024 | COT - LCPL - Gas Pressure Test | Passed | ||
| 08/23/2024 | COT - LCBU - Roof Nailing | Passed | ||
| 10/11/2024 | COT - LCBU - Exterior Clips/Sheathing | Passed | All of 3rd floor approved. 10/11/2024 | |
| 01/17/2025 | COT - LCME - Mechanical Intermediate | Passed | ||
| 01/17/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 01/17/2025 | COT - LCBU - Building Above Ceiling | Passed | ||
| 01/17/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 01/17/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 01/17/2025 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 01/17/2025 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 01/28/2025 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 03/25/2025 | BULD - Electrical Clearance | Passed | 3-25-25, ECO clearance issued for unit 7202. | |
| 05/20/2025 | TRSP - ROW - Final/Close-Out | Passed | Work completed on private property | |
| 05/27/2025 | COT - FCON - Fire - Final | Passed | ||
| 05/29/2025 | COT - LCEL - Electrical Final | Passed | 5-29-25: mechanical, plumbing, and electrical finals for unit's to Building 17 approved. | |
| 05/29/2025 | COT - LCME - Mechanical Final | Passed | 5-29-25: mechanical, plumbing, and electrical finals for unit's to Building 17 approved. | |
| 05/29/2025 | COT - LCPL - Plumbing Final | Passed | 5-29-25: mechanical, plumbing, and electrical finals for unit's to Building 17 approved. | |
| 05/29/2025 | COT - LCEL - Outdoor Lighting | Passed | 5-29-25, outdoor lighting on all u its for Building 17 approved. | |
| 05/30/2025 | COT - LCBU - Building Final | Passed | 5-30-25: Building 17 final for each unit approved. |