05/22/2025 COT - LCBU - Building Final  Partial Pass 5-22-25, Building 17 final on unit's 17304, 17306, 17204, 17206, 17104 (missing water closet/mirror), 17106 (missing bathroom mirror, kitchen light bulbs, bathroom vanity cabinet doors). Unit’s 17104 & 17106 will be reinspected when ready.
05/23/2025 COT - LCBU - Building Final  Partial Pass 5-23-25, Building 17 final on unit's 17101, 17102, 17201, 17202, 17301 (missing condensate float switch),17302 a/c blowing hot air.
05/27/2025 COT - LCBU - Building Final  Partial Pass 5-27-25: building final on unit's 17305, 17303, 17205, 17203, 17105, 17103 approved.However, several units are missing their medicine cabinets and although these items are not necessarily a code requirement; we will verify installation at a later date.Also, several A/C refrigerant caps to condensers missing at rooftop.
05/28/2025 COT - LCBU - Building Final  Partial Pass 5-28-25, building final on unit's 17307, 17308, 17208, 17307, 17107 approved, 17108 (missing bathtub trim)
05/29/2025 COT - LCBU - Building Final  Partial Pass 5-29-25: corrections listed from previous inspections to units in question have been corrected. Building final on all unit's from Building 17 are approved pending installation of vanity mirrors on a few units.
05/30/2025 COT - LCBU - Building Final  Passed 5-30-25: Building 17 final for each unit approved.