Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/22/2025 |
COT - LCEL - Electrical Final |
|
Partial Pass |
5-22-25, Building 17 final on unit's 17304, 17306, 17204, 17206, 17104 (missing water closet/mirror), 17106 (missing bathroom mirror, kitchen light bulbs, bathroom vanity cabinet doors). Unit’s 17104 & 17106 will be reinspected when ready. |
| 05/23/2025 |
COT - LCEL - Electrical Final |
|
Partial Pass |
5-23-25, Building 17 final on unit's 17101, 17102, 17201, 17202, 17301 (missing condensate float switch),17302 a/c blowing hot air. |
| 05/27/2025 |
COT - LCEL - Electrical Final |
|
Partial Pass |
5-27-25, partial pass for mechanical( missing a/c refrigerant caps on rooftop condensers)electrical, plumbing and outdoor lighting to unit's 17305, 17303, 17205, 17203, 17103, 17105. |
| 05/28/2025 |
COT - LCEL - Electrical Final |
|
Partial Pass |
5-28-25, building final, mechanical, electric, plumbing, outdoor lighting on unit's 17307, 17308, 17208, 17307, 17107 approved, 17108 (missing bathtub trim) |
| 05/29/2025 |
COT - LCEL - Electrical Final |
|
Passed |
5-29-25: mechanical, plumbing, and electrical finals for unit's to Building 17 approved. |