Permit: TC-MDP-0523-01103
Permit Details
Apply Date:
05/30/2023
Applicant:
HSLCS Permits
Description:
Building B three-story, 24 unit, apartment building model plans
Permit Reviews
Permit Number - TC-MDP-0523-01103
Permit Status: Complete
Permit Description: Building B three-story, 24 unit, apartment building model plans
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/13/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/16/2024 | APPROVED |
07/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/08/2024 | REQUIRES RESUBMIT |
06/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/24/2023 | APPROVED |
08/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 08/20/2024 | APPROVED |
09/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/18/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0523-01103
Permit Status: Complete
Permit Description: Building B three-story, 24 unit, apartment building model plans
Date | Description | Comments |
---|---|---|
04/21/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
04/21/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
07/24/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
04/21/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
04/21/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
05/30/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/21/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
08/20/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0523-01103
Permite Description: Building B three-story, 24 unit, apartment building model plans
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/21/2024 | COT - LCBU - Exterior Clips/Sheathing | N/A | Partial Pass | 2/21/24:First floor exterior clip and sheathing clips missing at interior shear walls. Anchor bolts spacing greater than shearwall schedule through first floor. |
11/27/2023 | COT - LCBU - Roof Nailing | N/A | Partial Pass | Floor nailing Level two. |
04/29/2024 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
09/10/2024 | COT - LCEL - Electrical Final | N/A | Partial Pass | 3rd tower south end approved. 9/10/2024 |
09/10/2024 | COT - LCME - Mechanical Final | N/A | Partial Pass | 3rd tower south end approved. 9/10/2024 |
09/10/2024 | COT - LCPL - Plumbing Final | N/A | Partial Pass | 3rd tower south end approved. 9/10/2024 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0523-01103
Permit Description: Building B three-story, 24 unit, apartment building model plans
Total Completed Inspections - 29
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/25/2023 | COT - LCPL - Rough Soil | Passed | ||
09/22/2023 | COT - LCPL - Yard Water Line | Passed | Yard water line is roughed in and under 60# of air pressure for Building #3. Okay to shade pipe and backfill trench. | |
09/27/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
09/27/2023 | COT - LCBU - Preslab | Passed | ||
09/27/2023 | COT - LCEL - Electrical Underground | Passed | ||
09/27/2023 | COT - LCEL - Grounding/Bonding | Passed | ||
02/21/2024 | COT - LCPL - Sewer | Passed | 2/21/24: HCS connection complete. Shading required | |
02/26/2024 | COT - LCBU - Exterior Clips/Sheathing | Passed | 2/21/24:First floor exterior clip and sheathing clips missing at interior shear walls. Anchor bolts spacing greater than shearwall schedule through first floor. 2/22/24 Second floor good to go. 2/26/24: third floor passed. |
|
02/28/2024 | COT - LCBU - Roof Nailing | Passed | ||
04/19/2024 | COT - LCBU - Framing | Passed | ||
04/22/2024 | COT - LCME - Mechanical Intermediate | Passed | 4/10/24: Canceled per Jacob 4/22/24: third and second floor passed. |
|
04/26/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
04/26/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
04/26/2024 | COT - LCME - Mechanical Above Ceiling | Passed | ||
04/26/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
04/26/2024 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
04/30/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
05/03/2024 | COT - HCBU - Interior Shear Bracing | Passed | 5/3/24: interior shear bracing passed. | |
06/11/2024 | BULD - Electrical Clearance | Passed | 6/11/24: TEP ECO 7355 S WILMOT RD Building 3 South Service #1 units (House Panel, 3103,3303,3203,3102,3202,3302,3301,3304,3204,3101,3104,3201) TEP ECO 7355 S WILMOT RD Building 3 North Service #2 units (3307,3207,3206,3107,3308,3306,3106,3105,3208,3305,3205,3108) |
|
09/05/2024 | COT - BULD - SWG Clearance | Passed | ||
09/05/2024 | COT - LCPL - Gas Pressure Test | Passed | ||
09/17/2024 | COT - FCON - Fire - Final | Passed | ||
09/18/2024 | COT - LCBU - Building Final | Passed | ||
09/18/2024 | COT - LCEL - Electrical Final | Passed | Roof inspection approved. 9/18/2024 | |
09/18/2024 | COT - LCME - Mechanical Final | Passed | Roof inspection approved. 9/18/2024 | |
09/18/2024 | COT - LCPL - Plumbing Final | Passed | Roof inspection approved. 9/18/2024 | |
09/18/2024 | ENGR Engineering Final | Passed | This building is ready to occupy | |
09/18/2024 | TRSP - ROW - Final/Close-Out | Passed | no impact to RoW | |
09/18/2024 | COT - LCEL - Outdoor Lighting | Passed |