Inspection Status: Canceled
Inspection History: COT - LCPL - Plumbing Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/10/2024 | COT - LCPL - Plumbing Intermediate | Canceled | 4/10/24: Canceled per Jacob | |
| 04/11/2024 | COT - LCPL - Plumbing Intermediate | Partial Pass | 4/10/24: Canceled per Jacob 4/11/24: Third floor plumbing intermediate passed. Pending DWV on third floor |
|
| 04/12/2024 | COT - LCPL - Plumbing Intermediate | Partial Pass | 4/10/24: Canceled per Jacob 4/11/24: Third floor plumbing intermediate passed. Pending DWV on third floor 4/12/24: Third floor plumbing intermediate passed. Pending DWV on third floor |
|
| 04/15/2024 | COT - LCPL - Plumbing Intermediate | Partial Pass | 4/10/24: Canceled per Jacob 4/11/24: Third floor plumbing intermediate passed. Pending DWV on third floor 4/12/24: Third floor plumbing intermediate passed. Pending DWV on third floor 4/15/24: DWV under test. Ok to insulate third floor. |
|
| 04/19/2024 | COT - LCPL - Plumbing Intermediate | Not Ready | ||
| 04/22/2024 | COT - LCPL - Plumbing Intermediate | Partial Pass | 4/10/24: Canceled per Jacob 4/11/24: Third floor plumbing intermediate passed. Pending DWV on third floor 4/12/24: Third floor plumbing intermediate passed. Pending DWV on third floor 4/15/24: DWV under test. Ok to insulate third floor. 4/22/24: second floor passed. |
|
| 04/23/2024 | COT - LCPL - Plumbing Intermediate | Not Ready | ||
| 04/24/2024 | COT - LCPL - Plumbing Intermediate | Partial Pass | 4/10/24: Canceled per Jacob 4/11/24: Third floor plumbing intermediate passed. Pending DWV on third floor 4/12/24: Third floor plumbing intermediate passed. Pending DWV on third floor 4/15/24: DWV under test. Ok to insulate third floor. 4/22/24: second floor passed. 4/23/24 called for roof drains, not ready 4/24/24: roof drains passed. |
|
| 04/26/2024 | COT - LCPL - Plumbing Intermediate | Passed |