Permit: TC-MDP-0426-00200
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
390 N COVILLE DR
Address NEW:
390 N COVILLE DR
Apply Date:
04/13/2026
Applicant:
Celina Rodriguez
Description:
Enclaves at Tumamoc 1609 Plan (Model Master Plan TC-MDP-1225-00793)
Permit Reviews
Permit Number - TC-MDP-0426-00200
Permit Status: Inspections complete
Permit Description: Enclaves at Tumamoc 1609 Plan (Model Master Plan TC-MDP-1225-00793)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/25/2026 | SPECIAL INSPECTION REVIEW v.1 | 09/25/2026 | APPROVED |
| 04/20/2026 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 04/28/2026 | APPROVED |
| 04/30/2026 | ADMINISTRATIVE v.2 | N/A | APPROVED |
| 04/28/2026 | ADMINISTRATIVE v.1 | N/A | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0426-00200
Permit Status: Inspections complete
Permit Description: Enclaves at Tumamoc 1609 Plan (Model Master Plan TC-MDP-1225-00793)
| Date | Description | Comments |
|---|---|---|
| 04/01/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. | |
| 04/23/2026 | Building permits associated with TD-DEV-1024-00280, Enclaves at Tumamoc, shall not be issued until resolution of Board of Adjustment case C10-26-02. Contact Nicholas Ross or Christopher Poirier for additional information and/or authorization to issue. | |
| 04/20/2026 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/21/2026 | Enclaves at Tumamoc Appeal | |
| 04/20/2026 | Prior to Inspections, please submit a Manual J Calculation. Step-by-Step instruction on how to resubmit: https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf | |
| 04/01/2026 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 04/20/2026 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 04/01/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 04/20/2026 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 04/01/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0426-00200
Permite Description: Enclaves at Tumamoc 1609 Plan (Model Master Plan TC-MDP-1225-00793)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/06/2026 | COT - RSEL - Electrical Final | N/A | Canceled | Canceled per contractor. 7/6/2026 |
| 09/23/2026 | ENGR Engineering Final | N/A | Not Ready | Outstanding conditions need to be satisfied prior to final. -HCS collar for cap needs to be glued to pipe in driveway. -Accessible Route will need to have post and cable fencing at both ends of the rear sidewalk removed. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0426-00200
Permit Description: Enclaves at Tumamoc 1609 Plan (Model Master Plan TC-MDP-1225-00793)
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/15/2026 | COT - RSPL - Backwater Valve | Passed | Passed 5/15/26 | |
| 05/15/2026 | COT - RSPL - Rough Soil | Passed | Passed 5/15/26 | |
| 05/15/2026 | COT - RSPL - Sewer | Passed | Passed 5/15/26 | |
| 05/18/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 05/18/2026 Approved per plan and reinforcement. Okay to pour. |
|
| 05/18/2026 | COT - RSBU - Preslab | Passed | 05/18/2026 Approved per plan and reinforcement. Okay to pour. |
|
| 05/27/2026 | COT - RSBU - Roof Nailing | Passed | 05/27/2026 Corrections made to missing anchor bolt washers at SW11 & SW13, added h2.5 clips to bearing point at girder, added nails to overdriven shear wall. Verified truss calcs. |
|
| 05/27/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 05/27/2026 Corrections made to missing anchor bolt washers at SW11 & SW13, added h2.5 clips to bearing point at girder, added nails to overdriven shear wall. Verified truss calcs. |
|
| 06/03/2026 | COT - RSPL - Gas Pressure Test | Passed | ||
| 06/04/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 06/08/2026 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/07/2026 | COT - RSEL - Electrical Final | Passed | ||
| 07/07/2026 | COT - RSME - Mechanical Final | Passed | ||
| 07/07/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 07/17/2026 | BULD - Electrical Clearance | Passed | ||
| 08/24/2026 | COT - RSPL - Yard Water Line | Passed | Passed | |
| 08/25/2026 | COT - BULD - SWG Clearance | Passed | 8-25-26: gas pressure test approved-SWG clearance issued. | |
| 09/23/2026 | RSBU - Building Progress | Passed | ||
| 09/30/2026 | COT - RSEL - Electrical Underground | Passed | 9/30/2026 All corrections made. |
|
| 09/30/2026 | COT - RSPL - Plumbing Final | Passed | 9/30/2026 All corrections made. |
|
| 09/30/2026 | ENGR Engineering Final | Passed | ||
| 09/30/2026 | RSBU - Building Final | Passed | 9/30/2026 All corrections made. Conditions satisfied. All utilities connected. |