Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
04/30/2024
Applicant:
Description:
VC 1465-130

Permit Reviews

Permit Number - TC-MDP-0424-00543
Permit Status: Inspections complete
Permit Description: VC 1465-130
Start Date Submittal Complete Date Status  
04/30/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 05/01/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0424-00543
Permit Status: Inspections complete
Permit Description: VC 1465-130
Total Outstanding Activity Conditions - 6
Date Name
04/30/2024 Post-Tension Inspection Report is required.
04/30/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
04/30/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
05/01/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
05/01/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
05/01/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-0424-00543
Permit Status: Inspections complete
Permit Description: VC 1465-130
Date Description Comments
05/01/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
04/30/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00543
Permite Description: VC 1465-130
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
05/30/2024 COT - RSBU - Exterior Clips/Sheathing N/A Re-inspection required 5/30/24: no plans on site called Karl multiple times and left voicemail. Address on job site required for future inspections.
05/30/2024 COT - RSBU - Roof Nailing N/A Re-inspection required 5/30/24: no plans on site called Karl multiple times and left voicemail. Address on job site required for future inspections.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00543
Permit Description: VC 1465-130
Total Completed Inspections - 21
Date Description Inspector Results Comments
05/08/2024 COT - RSPL - Rough Soil Passed
05/08/2024 COT - RSPL - Sewer Passed
05/08/2024 COT - RSPL - Yard Water Line Passed
05/20/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
05/20/2024 COT - RSBU - Preslab Passed
05/20/2024 COT - RSEL - Electrical Underground Passed
05/20/2024 COT - RSEL - Grounding/Bonding Passed
06/05/2024 COT - RSBU - Exterior Clips/Sheathing Passed
06/05/2024 COT - RSBU - Roof Nailing Passed
06/17/2024 BULD - Electrical Clearance Passed
06/17/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
06/17/2024 COT - RSPL - Gas Pressure Test Passed
06/25/2024 COT - RSBU - Interior Shear Bracing Passed
08/09/2024 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 8/9/2024
08/27/2024 COT - RSEL - Electrical Final Passed 8/27/2024 corrections have been made
08/27/2024 COT - RSEL - Outdoor Lighting Passed 8/27/2024 corrections have been made
08/27/2024 COT - RSME - Mechanical Final Passed 8/27/2024 corrections have been made
08/27/2024 COT - RSPL - Plumbing Final Passed 8/27/2024 corrections have been made
08/27/2024 RSBU - Building Final Passed 8/27/2024 corrections have been made
08/27/2024 RSBU - Building Progress Passed
08/28/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
RESERVES AT VALENCIA CROSSING - LOT 8 START_V1.PDF DOCUMENTS VIEW
RVC 8 SIC-2024-04-30_V1.PDF DOCUMENTS VIEW