Permit: TC-MDP-0424-00456
Permit Details
Apply Date:
04/17/2024
Applicant:
Joshua Swinney
Description:
Indiana Dunes Model Plan La Escalera
Permit Reviews
Permit Number - TC-MDP-0424-00456
Permit Status: Issued
Permit Description: Indiana Dunes Model Plan La Escalera
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/03/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 05/09/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0424-00456
Permit Status: Issued
Permit Description: Indiana Dunes Model Plan La Escalera
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
04/17/2024 | Post-Tension Inspection Report is required. |
04/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
05/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
05/08/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
05/08/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0424-00456
Permit Status: Issued
Permit Description: Indiana Dunes Model Plan La Escalera
Date | Description | Comments |
---|---|---|
04/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/17/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00456
Permite Description: Indiana Dunes Model Plan La Escalera
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/03/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
10/03/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00456
Permit Description: Indiana Dunes Model Plan La Escalera
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/30/2024 | COT - RSPL - Rough Soil | Passed | ||
05/30/2024 | COT - RSPL - Yard Water Line | Passed | ||
06/12/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are set, post tension cabling is properly installed and evenly spaced, rebar reinforcement is in place per plans, masa clips and shear wall hold downs are properly secured to form, subsoil is compacted, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island, and Ufer ground is installed in footing on garage side of house. | |
06/12/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, post tension cabling is properly installed and evenly spaced, rebar reinforcement is in place per plans, masa clips and shear wall hold downs are properly secured to form, subsoil is compacted, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island, and Ufer ground is installed in footing on garage side of house. | |
06/12/2024 | COT - RSEL - Electrical Underground | Passed | Concrete forms are set, post tension cabling is properly installed and evenly spaced, rebar reinforcement is in place per plans, masa clips and shear wall hold downs are properly secured to form, subsoil is compacted, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island, and Ufer ground is installed in footing on garage side of house. | |
06/12/2024 | COT - RSEL - Grounding/Bonding | Passed | Concrete forms are set, post tension cabling is properly installed and evenly spaced, rebar reinforcement is in place per plans, masa clips and shear wall hold downs are properly secured to form, subsoil is compacted, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island, and Ufer ground is installed in footing on garage side of house. | |
07/09/2024 | COT - RSBU - Roof Nailing | Passed | ||
07/12/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | 7/12/24: Support has been added for girder truss, missing RSP Clip has been installed, other has been properly nailed. Okay to proceed with rough-in. | |
09/19/2024 | COT - RSPL - Backwater Valve | Passed | ||
09/19/2024 | COT - RSPL - Sewer | Passed | ||
10/16/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 10/16/24: Shower pan is full of water, bottom plate has been completed, DWV is under water testt after being repaired from nail and staple puncher, all penetrations in top plate and bottom plate have been foamed, and shot pins have been added where needed. Okay to proceed with insulation and drywall installation. | |
11/13/2024 | COT - RSBU - Interior Shear Bracing | Passed | 11-13-24, approved. Okay to tape and texture |