Inspection Status: Passed
Inspection History: COT - RSBU - Excavation/Rebar/ZoningĀ
| Date |
Description |
Inspector |
Results |
Comments |
| 06/12/2024 |
COT - RSBU - Excavation/Rebar/ZoningĀ |
|
Passed |
Concrete forms are set, post tension cabling is properly installed and evenly spaced, rebar reinforcement is in place per plans, masa clips and shear wall hold downs are properly secured to form, subsoil is compacted, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island, and Ufer ground is installed in footing on garage side of house. |