Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: COT - RSBU - Preslab
Permit Number - TC-MDP-0424-00456
Inspection Description - COT - RSBU - Preslab
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/12/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, post tension cabling is properly installed and evenly spaced, rebar reinforcement is in place per plans, masa clips and shear wall hold downs are properly secured to form, subsoil is compacted, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island, and Ufer ground is installed in footing on garage side of house. |