Permit: TC-MDP-0324-00347
Permit Details
Apply Date:
03/26/2024
Applicant:
Brianna Quiroz
Description:
Roosevelt Model SFR La Estancia (Revision 1 Truss)
Permit Reviews
Permit Number - TC-MDP-0324-00347
Permit Status: Complete
Permit Description: Roosevelt Model SFR La Estancia (Revision 1 Truss)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/28/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 04/04/2024 | APPROVED |
12/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/26/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0324-00347
Permit Status: Complete
Permit Description: Roosevelt Model SFR La Estancia (Revision 1 Truss)
Date | Description | Comments |
---|---|---|
04/01/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
03/20/2024 | Post-Tension Inspection Report is required. | |
03/20/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
03/20/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
03/20/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0324-00347
Permit Description: Roosevelt Model SFR La Estancia (Revision 1 Truss)
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/23/2024 | COT - BULD - SWG Clearance | Passed | ||
07/23/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
07/25/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 7/25/2024 | |
07/25/2024 | COT - RSEL - Electrical Underground | Passed | ||
07/26/2024 | COT - RSPL - Rough Soil | Passed | Approved. Okay to backfill. Shading required. 7/26/2024 | |
07/26/2024 | COT - RSPL - Sewer | Passed | Approved. Okay to backfill. Shading required. 7/26/2024 | |
08/08/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/08/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
08/08/2024 | COT - RSBU - Preslab | Passed | ||
09/04/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Corrections were made. 9/4/2024 | |
09/09/2024 | COT - RSBU - Roof Nailing | Passed | ||
10/10/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Canceled per contractor. 9/3/2024 Leak at plumbing lines above kitchen area. Secure duct in first bedroom. Secure all vertical ABS lines. Secure loose electrical lines. Secure closet wall. Secure data line in garage. 10/9/2024 10/10/24: corrections made ok to proceed. |
|
10/25/2024 | COT - RSBU - Interior Shear Bracing | Passed | 10-25-24, okay to tape and texture. | |
10/29/2024 | BULD - Electrical Clearance | Passed | 10-29-24, panel approved for power. | |
01/08/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed final 1/8/25 | |
01/08/2025 | COT - RSME - Mechanical Final | Passed | Passed final 1/8/25 | |
01/08/2025 | COT - RSPL - Plumbing Final | Passed | Passed final 1/8/25 | |
01/08/2025 | RSBU - Building Final | Passed | Upstairs loft, hallway, and most of bedroom 3 do not have power 1/8/25 | |
01/09/2025 | ENGR Engineering Final | Passed | CO Ready | |
01/09/2025 | COT - RSEL - Electrical Final | Passed | 1/9/25 corrections made CLEARANCE ECO |
|
01/09/2025 | RSBU - Building Progress | Passed | 1/9/25 corrections made |