Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Address NEW:
2740 S BRANDYWINE LN
Apply Date:
02/07/2025
Applicant:
Chris Irby
Description:
1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)

Permit Reviews

Permit Number - TC-MDP-0225-00122
Permit Status: Complete
Permit Description: 1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Start Date Submittal Complete Date Status  
09/24/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/24/2025 REQUIRES RESUBMIT Review Details
11/13/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 11/14/2025 APPROVED Review Details
02/07/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.1 02/14/2025 APPROVED Review Details
01/22/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/23/2026 APPROVED Review Details
12/08/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/08/2025 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0225-00122
Permit Status: Complete
Permit Description: 1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Date Description Comments
02/07/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
02/07/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
02/07/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/07/2025 Post-Tension Inspection Report is required.
02/07/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
02/07/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
02/07/2025 Soil Compaction Special Inspection is Required.
11/24/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0225-00122
Permite Description: 1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
04/28/2025 COT - RSBU - Excavation/Rebar/Zoning N/A Canceled
04/28/2025 COT - RSBU - Preslab N/A Canceled
05/12/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Not Ready 1-Provide approved plans. 2-Remove and re-nail all shear and hood-down nails that missed the lumber intended got them. 3- Remove all extra sheeting, thermal ply, etc from roof to allow inspection.
05/12/2025 COT - RSBU - Roof Nailing N/A Not Ready 1-Provide approved plans. 2-Remove and re-nail all shear and hood-down nails that missed the lumber intended got them. 3- Remove all extra sheeting, thermal ply, etc from roof to allow inspection.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0225-00122
Permit Description: 1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Total Completed Inspections - 22
Date Description Inspector Results Comments
04/28/2025 BULD - Electrical Clearance Passed 4/28/25: ECO TEP CLEARANCE OK TO ENERGIZE.
04/28/2025 COT - RSEL - Electrical Underground Passed
04/28/2025 COT - RSPL - Backwater Valve Passed 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required
04/28/2025 COT - RSPL - Rough Soil Passed 4/28/25: plumbing underground per plan ok to proceed with backfill. Shading required
04/28/2025 COT - RSPL - Sewer Passed 4/28/25: plumbing underground per plan ok to proceed with backfill. Shading required
04/28/2025 COT - RSPL - Yard Water Line Passed 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required
05/01/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Passed 5/1/25 ready to pour concrete
05/01/2025 COT - RSBU - Preslab Passed Passed 5/1/25 ready to pour concrete
06/10/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 6/10/25 corrections made
06/10/2025 COT - RSBU - Roof Nailing Passed 6/10/25 corrections made
06/10/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Passed 6/10/25
06/10/2025 COT - RSEL - Grounding/Bonding Passed Passed 6/10/25
06/13/2025 COT - RSPL - Gas Pressure Test Passed Held pressure
06/25/2025 COT - RSBU - Interior Shear Bracing Passed Passed 6/25/25
07/30/2025 COT - BULD - SWG Clearance Passed 7/30/25
SOUTHWEST GAS CLEARANCE: SWG
07/31/2025 COT - RSEL - Electrical Final Passed
07/31/2025 COT - RSEL - Outdoor Lighting Passed
07/31/2025 COT - RSME - Mechanical Final Passed
07/31/2025 COT - RSPL - Plumbing Final Passed
07/31/2025 RSBU - Building Progress Passed
08/04/2025 RSBU - Building Final Passed Passed by Robert Chandler
08/07/2025 ENGR Engineering Final Passed Site is safe and accessible. Everything completed in accordance with approved plans.

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL (SSRS).PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
RIVENDELL LOT 24-START_V1.PDF DOCUMENTS VIEW
RIVENDELL LOT 24 SPECIAL INSPECTION CERT-2740 S BRANDYWINE LN-2025-02-07_V1.PDF DOCUMENTS VIEW