Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
9571 E WYNALDA DR
Apply Date:
04/03/2025
Applicant:
Celina Rodriguez
Description:
Mirador Point 1909 Plan (Model master plan TC-MDP-0125-00034)

Permit Reviews

Permit Number - TC-MDP-0225-00100
Permit Status: Inspections complete
Permit Description: Mirador Point 1909 Plan (Model master plan TC-MDP-0125-00034)
Start Date Submittal Complete Date Status  
04/03/2025 SITE FROM MODEL PERMIT - PRODUCTION v.1 04/14/2025 REQUIRES RESUBMIT Review Details
05/06/2025 RESTAMP - RESIDENTIAL v.1 05/09/2025 APPROVED Review Details
04/17/2025 SITE FROM MODEL PERMIT - PRODUCTION v.2 04/24/2025 REQUIRES RESUBMIT Review Details
05/02/2025 SITE FROM MODEL PERMIT - PRODUCTION v.3 05/06/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0225-00100
Permit Status: Inspections complete
Permit Description: Mirador Point 1909 Plan (Model master plan TC-MDP-0125-00034)
Total Outstanding Activity Conditions - 4
Date Name
04/11/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/11/2025 Post-Installed Anchor Inspection Report is required.
04/11/2025 Post-Tension Inspection Report is required.
04/11/2025 Soil Compaction Special Inspection is Required.

Conditions

Permit Number - TC-MDP-0225-00100
Permit Status: Inspections complete
Permit Description: Mirador Point 1909 Plan (Model master plan TC-MDP-0125-00034)
Date Description Comments
02/07/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
02/07/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
04/11/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0225-00100
Permite Description: Mirador Point 1909 Plan (Model master plan TC-MDP-0125-00034)
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
05/14/2025 COT - BULD - SWG Clearance N/A Not Applicable No gas service on site.
05/14/2025 COT - RSPL - Gas Pressure Test N/A Not Applicable No gas service on site.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0225-00100
Permit Description: Mirador Point 1909 Plan (Model master plan TC-MDP-0125-00034)
Total Completed Inspections - 20
Date Description Inspector Results Comments
05/14/2025 COT - RSPL - Backwater Valve Passed
05/14/2025 COT - RSPL - Rough Soil Passed
05/14/2025 COT - RSPL - Sewer Passed
05/29/2025 COT - RSEL - Electrical Underground Passed 5-29-25, electrical underground approved.
06/03/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 6-3-25: excavation/rebar and setbacks verified per plans. Okay to pour concrete.
06/03/2025 COT - RSBU - Preslab Passed 6-3-25: preslab, excavation /rebar and setbacks verified per plans. Okay to pour concrete.
06/30/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 6/30/25 corrections made
06/30/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Passed 6/30/25
06/30/2025 COT - RSBU - Roof Nailing Passed 6/30/25 corrections made
06/30/2025 COT - RSEL - Grounding/Bonding Passed 6/30/25 passed
07/14/2025 COT - RSBU - Interior Shear Bracing Passed 7.14.21 fastener spacing and penetration still not per plan/code
07/17/2025 BULD - Electrical Clearance Passed Passed 7/17/25 CLEARANCE ECO
09/09/2025 RSBU - Building Progress Passed
09/09/2025 ENGR Engineering Final Passed Site is safe and complete in accordance with approved plans.
09/11/2025 COT - RSEL - Electrical Final Passed 9.11.25
APPROVED
09/11/2025 COT - RSEL - Outdoor Lighting Passed 9.11.25
APPROVED
09/11/2025 COT - RSME - Mechanical Final Passed 9.11.25
APPROVED
09/11/2025 COT - RSPL - Plumbing Final Passed 9.11.25
APPROVED
09/11/2025 RSBU - Building Final Passed 9.11.25
APPROVED
09/11/2025 COT - RSPL - Yard Water Line Passed 9.11.25
APPROVED

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
MIRADOR POINT - LOT 186 START_V3.PDF DOCUMENTS VIEW