Permit: TC-COM-1224-02281
Permit Details
Apply Date:
12/02/2024
Applicant:
Daniel Berg
Description:
new tenant improvement that requires electrical, mechanical. Plumbing, architectural and structural. the building remains as is. 96000.00
Permit Reviews
Permit Number - TC-COM-1224-02281
Permit Status: Complete
Permit Description: new tenant improvement that requires electrical, mechanical. Plumbing, architectural and structural. the building remains as is. 96000.00
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/22/2025 | APPROVED |
| 06/02/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/04/2025 | APPROVED |
| 02/06/2025 | RESTAMP - COMMERCIAL v.1 | 02/06/2025 | APPROVED |
| 01/27/2025 | COMMERCIAL REVIEW - FULL v.2 | 02/06/2025 | APPROVED |
| 12/09/2024 | COMMERCIAL REVIEW - FULL v.1 | 01/02/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1224-02281
Permit Status: Complete
Permit Description: new tenant improvement that requires electrical, mechanical. Plumbing, architectural and structural. the building remains as is. 96000.00
| Date | Description | Comments |
|---|---|---|
| 02/05/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 12/23/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 12/24/2024 | NESHAP Permit is required. (Utilized with commercial demolition permits) | |
| 12/23/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1224-02281
Permite Description: new tenant improvement that requires electrical, mechanical. Plumbing, architectural and structural. the building remains as is. 96000.00
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/13/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 04/22/2025 | COT - HCBU - Framing | N/A | Partial Pass | Soffit at desk area 102. Approved. Exterior new infill wall at lounge entry 117 per wall type schedules. Okay to proceed progress areas. 4/22/2025 |
| 02/12/2025 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Ok to Hard Lid |
| COT - FCON - Alarm - Final | N/A | Not Ready | Fire Alarm System not installed yet. | |
| 05/30/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Approved for level2 TCO. FACP ad riser signage. EM lights and exit signs on south side of building. All debris out of egress paths. Labeled keys in Knox box. Inner doors main entrance sticking. Need dedicated function alarm to supervise sprinkler, ansul, and CO2 detector(if applicable).. If debris, EM lights and exit signs and exit door issues are addressed by 6/2/2025, a level 4 TCO can be obtained. Revised plans must be submitted and all dedicated supervisory systems must pass inspection before final. |
| 06/03/2025 | COT - LCBU - Building Final | N/A | Partial Pass | Ok for level 1 TCO 6/3/25: OKAY FOR LEVEL 4 TCO. Pending fire |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1224-02281
Permit Description: new tenant improvement that requires electrical, mechanical. Plumbing, architectural and structural. the building remains as is. 96000.00
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2025 | COT - LCPL - Rough Soil | Passed | ||
| 04/11/2025 | COT - BULD - SWG Clearance | Passed | Clearance for Southwest Gas. 4/11/2025 | |
| 04/21/2025 | COT - HCBU - Preslab | Passed | ||
| 04/21/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 05/01/2025 | COT - LCPL - Gas Pressure Test | Passed | ||
| 05/28/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 05/28/2025 | COT - LCME - Mechanical Intermediate | Passed | ||
| 05/28/2025 | COT - HCBU - Framing | Passed | ||
| 05/28/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 05/30/2025 | ENGR Engineering Final | Passed | Site is good. CofO ready. | |
| 05/30/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 06/03/2025 | COT - LCPL - Plumbing Final | Passed | ||
| 06/03/2025 | COT - LCME - Mechanical Final | Passed | ||
| 06/03/2025 | COT - LCEL - Electrical Final | Passed | ||
| 12/03/2025 | COT - FCON - Alarm - Final | Passed | ||
| 12/03/2025 | COT - FCON - Fire - Final | Passed | ||
| 12/03/2025 | COT - LCBU - Building Final | Passed |