Permit: TC-COM-1223-02946
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
3701 E 3RD ST BLDG 3
Address NEW:
3701 E 3RD ST BLDG 3
Apply Date:
12/27/2023
Applicant:
Elizabeth Farkas
Description:
BLDG 3 - New multifamily building on existing site, minor renovations to existing one-bedroom casitas, and site improvements. Development Plan is currently under review but DP sheets have been provided for reference.
Permit Reviews
Permit Number - TC-COM-1223-02946
Permit Status: Inspections
Permit Description: BLDG 3 - New multifamily building on existing site, minor renovations to existing one-bedroom casitas, and site improvements. Development Plan is currently under review but DP sheets have been provided for reference.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/24/2024 | REQUIRES RESUBMIT |
| 10/24/2024 | COMMERCIAL REVIEW - FULL v.2 | 10/29/2024 | APPROVED |
| 05/21/2024 | COMMERCIAL REVIEW - FULL v.3 | 05/22/2024 | APPROVED |
| 09/03/2024 | COMMERCIAL REVIEW - FULL v.1 | 10/02/2024 | REQUIRES RESUBMIT |
| 08/22/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/26/2024 | APPROVED |
| 03/14/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/12/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-1223-02946
Permit Status: Inspections
Permit Description: BLDG 3 - New multifamily building on existing site, minor renovations to existing one-bedroom casitas, and site improvements. Development Plan is currently under review but DP sheets have been provided for reference.
Total Outstanding Activity Conditions - 10
| Date | Name |
|---|---|
| 03/20/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 03/20/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 03/20/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 03/20/2024 | Masonry Inspection Report submittal review is required. |
| 03/20/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 03/20/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 03/20/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 03/20/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
| 03/20/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
| 05/10/2024 | Prior to project being finalized applicant must provide the Pima County Recorders' sequence number for the dedication of the right of way for parking to the south of the site. |
Conditions
Permit Number - TC-COM-1223-02946
Permit Status: Inspections
Permit Description: BLDG 3 - New multifamily building on existing site, minor renovations to existing one-bedroom casitas, and site improvements. Development Plan is currently under review but DP sheets have been provided for reference.
| Date | Description | Comments |
|---|---|---|
| 12/27/2023 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 12/27/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 05/22/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 03/19/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 03/19/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-1223-02946
Permite Description: BLDG 3 - New multifamily building on existing site, minor renovations to existing one-bedroom casitas, and site improvements. Development Plan is currently under review but DP sheets have been provided for reference.
Total Outstanding Inspections - 23
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/13/2026 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 04/13/2026 | COT - HCME - Mechanical Progress | N/A | Not Applicable | |
| 04/13/2026 | COT - HCEL - Electrical Above Ceiling | N/A | Not Applicable | |
| 04/13/2026 | COT - HCME - Mechanical Intermediate | N/A | Not Applicable | |
| 04/13/2026 | COT - HCBU - Building Final | N/A | Not Applicable | |
| 04/13/2026 | COT - HCEL - Electrical Final | N/A | Not Applicable | |
| 04/13/2026 | COT - HCEL - Electrical Progress | N/A | Not Applicable | |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | ||
| COT - FCON - Alarm - Final | N/A | Not Ready | ||
| 04/13/2026 | COT - HCBU - Building Progress | N/A | Not Applicable | |
| 04/13/2026 | COT - HCME - Mechanical Above Ceiling | N/A | Not Applicable | |
| 04/13/2026 | COT - HCPL - Plumbing Above Ceiling | N/A | Not Applicable | |
| 04/13/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
| 04/13/2026 | COT - HCPL - Plumbing Intermediate | N/A | Not Applicable | |
| 04/13/2026 | COT - HCPL - Plumbing Final | N/A | Not Applicable | |
| 04/13/2026 | ENGR Engineering Final | N/A | Not Ready | Bldg. # needs to be on building for emergency services. Sidewalk panel (3rd panel) in front of front door, where it connects to new sidewalk in front of bldg. 9 has cross slope over 2% |
| 04/13/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| COT - FCON - Fire - Final | N/A | Not Ready | ||
| 04/13/2026 | COT - HCME - Mechanical Final | N/A | Not Applicable | |
| 04/13/2026 | COT - HCBU - Framing | N/A | Not Applicable | |
| 04/13/2026 | COT - HCPL - Plumbing Progress | N/A | Not Applicable | |
| 04/13/2026 | COT - HCEL - Electrical Intermediate | N/A | Not Applicable | |
| 04/13/2026 | COT - HCBU - Building Above Ceiling | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-1223-02946
Permit Description: BLDG 3 - New multifamily building on existing site, minor renovations to existing one-bedroom casitas, and site improvements. Development Plan is currently under review but DP sheets have been provided for reference.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/13/2026 | TRSP - ROW - Final/Close-Out | Passed |