Permit: TC-COM-1222-00312
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
3350 E HEMISPHERE LP
Address NEW:
3350 E HEMISPHERE LP
Apply Date:
12/16/2022
Applicant:
Lynette Hoff
Description:
Tenant Improvement - Converting an office space located on the first floor into testing lab
Permit Reviews
Permit Number - TC-COM-1222-00312
Permit Status: Issued
Permit Description: Tenant Improvement - Converting an office space located on the first floor into testing lab
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/30/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/26/2023 | REQUIRES RESUBMIT |
| 03/10/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/06/2023 | APPROVED |
Conditions
Permit Number - TC-COM-1222-00312
Permit Status: Issued
Permit Description: Tenant Improvement - Converting an office space located on the first floor into testing lab
| Date | Description | Comments |
|---|---|---|
| 12/30/2022 | Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512 | |
| 04/06/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-1222-00312
Permite Description: Tenant Improvement - Converting an office space located on the first floor into testing lab
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/04/2023 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 10/4/23: Clearance to power up transformer for panel L-K4 and L-K4UPS panel |
| 06/14/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | framing inspection |
| 03/20/2024 | COT - HCBU - Framing | N/A | Not Ready | |
| 03/20/2024 | COT - HCEL - Electrical Final | N/A | Not Ready | |
| 05/23/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | 5/23/24: badging issue regarding cleared inspector for job site. Will get clearance and badging for Gustavo for future inspections. |
| 05/23/2024 | COT - HCME - Mechanical Intermediate | N/A | Not Ready | 5/23/24: badging issue regarding cleared inspector for job site. Will get clearance and badging for Gustavo for future inspections. |
| 05/23/2024 | COT - HCEL - Electrical Intermediate | N/A | Not Ready | 5/23/24: badging issue regarding cleared inspector for job site. Will get clearance and badging for Gustavo for future inspections. |
| 03/20/2024 | ENGR Engineering Final | N/A | Canceled | There was a mix up in badgering for this job which requires a temporary badge. I will get it figured out so we can get this handled. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-1222-00312
Permit Description: Tenant Improvement - Converting an office space located on the first floor into testing lab
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/13/2023 | COT - HCBU - Building Above Ceiling | Passed | 9/13/23: Passed by Gustavo Armenta. ok to proceed | |
| 09/13/2023 | COT - HCEL - Electrical Above Ceiling | Passed | 9/13/23: Passed by Gustavo Armenta. ok to proceed Call ahead 10-15 minutes. Jeff 520-496-0076 |
|
| 09/13/2023 | COT - HCME - Mechanical Above Ceiling | Passed | 9/13/23: Passed by Gustavo Armenta. also inspected compressed air piping from main. ok to proceed | |
| 10/04/2023 | BULD - Electrical Clearance | Passed | 10/4/23: Clearance to power up transformer for panel L-K4 and L-K4UPS panel | |
| 10/09/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 10/9/23 footings for Crain inspected per revision B 6/28/23 ok to place concrete | |
| 03/20/2024 | COT - HCEL - Electrical Progress | Passed | ||
| 03/20/2024 | COT - HCBU - Building Progress | Passed | ||
| 03/18/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 05/24/2024 | COT - HCBU - Framing | Passed | ||
| 05/24/2024 | COT - HCEL - Electrical Final | Passed | ||
| 05/24/2024 | COT - HCME - Mechanical Final | Passed | ||
| 05/24/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 05/24/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 05/24/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 06/28/2024 | COT - FCON - Alarm - Final | Passed | ||
| 06/28/2024 | COT - FCON - Fire - Final | Passed | ||
| 06/24/2024 | ENGR Engineering Final | Passed | No exterior work was performed, interior TI only | |
| 06/28/2024 | COT - HCBU - Building Final | Passed | ||
| 06/28/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 06/28/2024 | COT - HCBU - CofO | Passed |