Permit: TC-COM-1222-00236
Permit Details
Apply Date:
12/05/2022
Applicant:
Brianna Uy
Description:
950 SF drive-through coffee shop with customer walk-up window
Permit Reviews
Permit Number - TC-COM-1222-00236
Permit Status: Complete
Permit Description: 950 SF drive-through coffee shop with customer walk-up window
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/25/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/26/2024 | APPROVED |
04/19/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/22/2024 | APPROVED |
04/25/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/25/2024 | APPROVED |
04/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/12/2024 | APPROVED |
11/07/2023 | RESTAMP - COMMERCIAL v.1 | 11/07/2023 | APPROVED |
12/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/02/2024 | APPROVED |
09/08/2023 | COMMERCIAL REVIEW - FULL v.4 | 10/04/2023 | REQUIRES RESUBMIT |
01/28/2023 | COMMERCIAL REVIEW - FULL v.2 | 08/18/2023 | REQUIRES RESUBMIT |
08/18/2023 | COMMERCIAL REVIEW - FULL v.3 | 09/07/2023 | REQUIRES RESUBMIT |
12/13/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/13/2022 | REQUIRES RESUBMIT |
11/03/2023 | COMMERCIAL REVIEW - FULL v.5 | 11/07/2023 | APPROVED |
Conditions
Permit Number - TC-COM-1222-00236
Permit Status: Complete
Permit Description: 950 SF drive-through coffee shop with customer walk-up window
Date | Description | Comments |
---|---|---|
04/12/2024 | AIR BALANCING REPORT IS REQUIRED. | |
04/12/2024 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. | |
04/12/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
04/12/2024 | COMMISSIONING REPORT IS REQUIRED. | |
04/19/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
07/28/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
04/12/2024 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
08/18/2023 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. | |
04/12/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
09/28/2023 | NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL #P23WC00286 IS ISSUED A DISCHARGE AUTHORIZATION BY PDEQ | |
04/12/2024 | Masonry Inspection Report submittal review is required. | |
04/12/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
04/12/2024 | Please submit a separate sign permit for an signs associated with this projet. | |
07/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/24/2024 | Separate submittal to PC RWRD is required for new conditions to sewer, new meter and upsized water meters. Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
04/12/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
04/12/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
04/12/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
08/18/2023 | WATER STERILIZATION REPORT IS REQUIRED. | |
04/12/2024 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1222-00236
Permite Description: 950 SF drive-through coffee shop with customer walk-up window
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/09/2024 | COT - HCEL - Grounding/Bonding | N/A | Not Ready | |
01/02/2024 | COT - HCPL - Rough Soil | N/A | Partial Pass | 1/2/23 plumbing under slab ok to cover |
02/08/2024 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | |
01/16/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Not Ready | please re fee if electrical conduits are not corrected on next inspection, do not block out footer for roof drains, place proper pipe with protection. |
01/11/2024 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 1/10/24: trash enclosure reinforcement per plan ok to grout and top out per Detail A9.0/9 1/11/24: Preslab reinforcement per plan at trash enclosure. Ok to pour. |
01/16/2024 | COT - HCBU - Preslab | N/A | Not Ready | See previous comments |
02/13/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 2/13/24: electrical in wall rough-in per plans ok to proceed, electrical at walk-thru complete. pending above ceiling in ceiling grid areas. |
01/11/2024 | COT - HCEL - Electrical Underground | N/A | Partial Pass | No electrical can be run longitudinally through footers 1/11/24: electrical underground in slab passed ok to backfill. (2) 4" conduit and (1) 2" conduit from secondary to building. Ok to backfill 1/11/24: Preslab reinforcement per plan at trash enclosure. Ok to pour. |
02/13/2024 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 1/31/24: 3/4 pex to to trash enclosure ok to backfill. 2/13/24: plumbing intermediate in walls per plan ok to proceed. Pending above ceiling. |
01/05/2024 | COT - HCPL - Sewer | N/A | Partial Pass | Four inch waste line from building to grease trap. Ok to cover progress areas. |
12/29/2023 | COT - HCPL - Yard Water Line | N/A | Partial Pass | 12/29/23: 2" Main water line ran from meter to building per code ok to back fill. 1" irrigation ran from meter to back flow preventer connection (pending connection) |
04/04/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
02/22/2024 | COT - HCEL - Outdoor Lighting | N/A | Partial Pass | 2/22/24: 4 light pole base's reinforcement per plan ok to proceed. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1222-00236
Permit Description: 950 SF drive-through coffee shop with customer walk-up window
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/17/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
01/22/2024 | COT - HCPL - Rough Soil | Passed | ||
02/07/2024 | COT - HCBU - Roof Nailing | Passed | ||
02/08/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
02/13/2024 | COT - HCBU - Framing | Passed | ||
03/21/2024 | BULD - Electrical Clearance | Passed | 3/21/2024. Clearance for TEP ECO. | |
04/02/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
04/02/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
04/02/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
04/04/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
04/04/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
04/04/2024 | COT - HCBU - Preslab | Passed | ||
04/04/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
04/04/2024 | COT - HCEL - Electrical Underground | Passed | ||
04/04/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
04/04/2024 | COT - HCPL - Sewer | Passed | ||
04/04/2024 | COT - HCPL - Yard Water Line | Passed | ||
04/04/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
04/04/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
04/04/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
04/11/2024 | ENGR Engineering Final | Passed | Handrails have been installed located at the NE sidewalk leading to trash enclosure. All pedestrian crossing located at drive thru leading to trash enclosure and SE corner off parking lot leading to public sidewalk are under 2% grade. |
|
04/16/2024 | COT - HCEL - Electrical Final | Passed | ||
04/16/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
04/17/2024 | COT - FCON - Fire - Final | Passed | ||
04/18/2024 | COT - HCBU - Building Final | Passed | ||
04/18/2024 | COT - HCME - Mechanical Final | Passed | ||
04/18/2024 | COT - HCPL - Plumbing Final | Passed |