Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/05/2024 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | No rebar placed in waste trench line. Ok to cover progress areas. | |
| 01/08/2024 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 01/16/2024 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | please re fee if electrical conduits are not corrected on next inspection, do not block out footer for roof drains, place proper pipe with protection. | |
| 01/17/2024 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Partial for three column footers north side 1/17/24: reinforcement per plans at slab ok to pour. Corrections were made. |
|
| 01/19/2024 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| COT - HCBU - Excavation/Rebar/Zoning | Passed |