Permit: TC-COM-1125-02138
Permit Details
Apply Date:
11/21/2025
Applicant:
Cathy Moreno
Description:
Remodel. Update building finishes. Remove roof HVACs & replace with new on ground level with screen wall. Repair HVAC roof openings. Plumbing fixtures replacements. Electrical panel work disconnect/reconnect. Replace door formerly covered.
Permit Reviews
Permit Number - TC-COM-1125-02138
Permit Status: Inspections
Permit Description: Remodel. Update building finishes. Remove roof HVACs & replace with new on ground level with screen wall. Repair HVAC roof openings. Plumbing fixtures replacements. Electrical panel work disconnect/reconnect. Replace door formerly covered.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2026 | COMMERCIAL REVIEW - FULL v.3 | 02/17/2026 | APPROVED |
| 02/17/2026 | RESTAMP - COMMERCIAL v.1 | 02/18/2026 | APPROVED |
| 11/26/2025 | COMMERCIAL REVIEW - FULL v.1 | 12/18/2025 | REQUIRES RESUBMIT |
| 01/09/2026 | COMMERCIAL REVIEW - FULL v.2 | 02/02/2026 | REQUIRES RESUBMIT |
| 03/31/2026 | ADMINISTRATIVE v.2 | N/A | IN REVIEW |
| 02/18/2026 | ADMINISTRATIVE v.1 | 02/18/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-1125-02138
Permit Status: Inspections
Permit Description: Remodel. Update building finishes. Remove roof HVACs & replace with new on ground level with screen wall. Repair HVAC roof openings. Plumbing fixtures replacements. Electrical panel work disconnect/reconnect. Replace door formerly covered.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 02/17/2026 | AIR BALANCING REPORT IS REQUIRED. |
| 07/30/2026 | Prior to project being finalized applicant must remove all temporary structures associated with TZ-PMT-0726-00064. |
Conditions
Permit Number - TC-COM-1125-02138
Permit Status: Inspections
Permit Description: Remodel. Update building finishes. Remove roof HVACs & replace with new on ground level with screen wall. Repair HVAC roof openings. Plumbing fixtures replacements. Electrical panel work disconnect/reconnect. Replace door formerly covered.
| Date | Description | Comments |
|---|---|---|
| 11/26/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 11/26/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-1125-02138
Permite Description: Remodel. Update building finishes. Remove roof HVACs & replace with new on ground level with screen wall. Repair HVAC roof openings. Plumbing fixtures replacements. Electrical panel work disconnect/reconnect. Replace door formerly covered.
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/17/2026 | COT - LCEL - Electrical Underground | N/A | Partial Pass | 9/17/26: 3-1" schedule conduits for disconnect verified. Okay to backfill progress areas. |
| 09/17/2026 | COT - LCBU - Preslab | N/A | Partial Pass | 9/17/26: preslqb/excavation/reinforcement for cmu footing verified per detail. Okay for concrete placement. |
| 10/06/2026 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | 10/6/26: in wall/above ceiling electrical verified per plans. Okay to continue with construction at progress areas. |
| 10/15/2026 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | 10/15/26: drywall screw inspection throughout building approved-okay for tape & texture. |
| 11/10/2026 | COT - LCEL - Electrical Final | N/A | Partial Pass | 11/10/26: add a GFCI receptacle at guest house's laundry room and submit updated panel schedules for MP-1 & MP-2. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-1125-02138
Permit Description: Remodel. Update building finishes. Remove roof HVACs & replace with new on ground level with screen wall. Repair HVAC roof openings. Plumbing fixtures replacements. Electrical panel work disconnect/reconnect. Replace door formerly covered.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/03/2026 | BULD - Electrical Clearance | Passed | 9-3-26: okay to energize meter 154611112. INCR clearance issued to TEP. | |
| 10/06/2026 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 10/6/26: verified reinforcement/bond beam at cmu wall at south end of building-grouted at 5'. | |
| 11/10/2026 | COT - LCME - Mechanical Intermediate | Passed | 11/10/26: mechanical intermediates approved. Okay to install ceiling tiles. |