Permit Details

Status:
Complete
Type:
Commercial Building
Address:
602 E 24TH ST
Address NEW:
602 E 24TH ST
Apply Date:
11/14/2024
Applicant:
Garett Cunningham
Description:
INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.

Permit Reviews

Permit Number - TC-COM-1124-02200
Permit Status: Complete
Permit Description: INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
Start Date Submittal Complete Date Status  
06/23/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/23/2025 APPROVED Review Details
11/15/2024 COMMERCIAL REVIEW - FULL v.1 12/10/2024 REQUIRES RESUBMIT Review Details
12/04/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/08/2025 APPROVED Review Details
01/06/2025 COMMERCIAL REVIEW - FULL v.2 01/30/2025 APPROVED Review Details
01/30/2025 RESTAMP - COMMERCIAL v.1 01/31/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-1124-02200
Permit Status: Complete
Permit Description: INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
Date Description Comments
01/27/2025 AIR BALANCING REPORT IS REQUIRED.
11/15/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
11/21/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
01/06/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
01/27/2025 WATER STERILIZATION REPORT IS REQUIRED.
11/21/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1124-02200
Permite Description: INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
04/01/2025 COT - LCEL - Grounding/Bonding N/A Partial Pass 4-1-25, partial pass on grounding. Will verify proper grounding/bonding after electrical wires are pulled for Type 3R Enclosure. 2-3" Schedule 40 conduits in place from transformer to new enclosure-okay to backfill pending TEP approval.
04/01/2025 COT - LCPL - Rough Soil N/A Partial Pass 4-1-25, underground plumbing inside of building verified under test and per approved plans. PEX at 60psi and sewer line in same trench-okay to backfill approximately 300' with shading materials. Maintain a 12" clearance between PEX and sewer. Also, have architect/engineer submit a revision for installation of additional backflow preventer.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1124-02200
Permit Description: INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
Total Completed Inspections - 15
Date Description Inspector Results Comments
04/28/2025 COT - LCPL - Plumbing Intermediate Passed 4-28-25, plumbing intermediate approved.
05/01/2025 COT - LCEL - Electrical Intermediate Passed 5-1-25, electrical intermediate inspection approved. Okay to install hard lids at progress areas.
05/01/2025 COT - LCEL - Grounding/Bonding Passed 5-1-25, grounding/bonding approved.
05/01/2025 BULD - Electrical Clearance Passed 5-1-25, panels are okay to be energized. INCR clearance sent to TEP.
05/01/2025 COT - LCME - Mechanical Intermediate Passed 5-1-25, mechanical above ceiling approved. Okay to continue with installation of hard lids.
10/10/2025 COT - LCBU - Framing Passed
10/10/2025 COT - LCPL - Rough Soil Passed
10/10/2025 COT - LCBU - Building Final Passed
10/10/2025 COT - LCEL - Electrical Final Passed
10/10/2025 COT - LCME - Mechanical Final Passed
10/10/2025 COT - LCPL - Plumbing Final Passed
10/10/2025 ENGR Engineering Final Passed Site is clear.
10/10/2025 COT - LCEL - Electrical Above Ceiling Passed
10/10/2025 COT - FCON - Sprinkler - Final Passed
11/12/2025 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL (SSRS).PDF DOCUMENTS VIEW
GRENIER ENGINEERING - ASSURED DESTRUCTION C OF O CLARIFICATION 11-16-25-2025-12-01_V1.PDF DOCUMENTS VIEW
24156 - STRUCTURAL CALCULATIONS - 11-11-24_V1.PDF DOCUMENTS VIEW
CHLORINATION WATER TEST REPORT - 25F0395_1 TURNERRES 06 16 2025 1218-2025-06-20_V1.PDF DOCUMENTS VIEW
TEST AND BALANCE REPORT - ASSUREDDOCUMENTDESTRUCTION_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-24078-ASSUREDDOCUMENTDESTRUCTION_PERMITSET_2501_03_V2.PDF DOCUMENTS VIEW
24293 SYSTEMS DESIGN REPORT_V1.PDF DOCUMENTS VIEW