Permit: TC-COM-1124-02200
Permit Details
Apply Date:
11/14/2024
Applicant:
Garett Cunningham
Description:
INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
Permit Reviews
Permit Number - TC-COM-1124-02200
Permit Status: Complete
Permit Description: INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/23/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/23/2025 | APPROVED |
| 11/15/2024 | COMMERCIAL REVIEW - FULL v.1 | 12/10/2024 | REQUIRES RESUBMIT |
| 12/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/08/2025 | APPROVED |
| 01/06/2025 | COMMERCIAL REVIEW - FULL v.2 | 01/30/2025 | APPROVED |
| 01/30/2025 | RESTAMP - COMMERCIAL v.1 | 01/31/2025 | APPROVED |
Conditions
Permit Number - TC-COM-1124-02200
Permit Status: Complete
Permit Description: INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
| Date | Description | Comments |
|---|---|---|
| 01/27/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 11/15/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 11/21/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 01/06/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 01/27/2025 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 11/21/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1124-02200
Permite Description: INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2025 | COT - LCEL - Grounding/Bonding | N/A | Partial Pass | 4-1-25, partial pass on grounding. Will verify proper grounding/bonding after electrical wires are pulled for Type 3R Enclosure. 2-3" Schedule 40 conduits in place from transformer to new enclosure-okay to backfill pending TEP approval. |
| 04/01/2025 | COT - LCPL - Rough Soil | N/A | Partial Pass | 4-1-25, underground plumbing inside of building verified under test and per approved plans. PEX at 60psi and sewer line in same trench-okay to backfill approximately 300' with shading materials. Maintain a 12" clearance between PEX and sewer. Also, have architect/engineer submit a revision for installation of additional backflow preventer. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1124-02200
Permit Description: INTERIOR T. I.. +/- 1062 SF OFFICE ADDED TO EXIST SPACE. REST OF SPACE IS STORAGE & WAREHOUSE. 3 NEW OPENINGS IN EXIST CONCRETE TILT PANEL WALLS. MECHANICAL, PLUMBING. ELECTRICAL TO BE ADDED THROUGHOUT OFFICE AND WAREHOUSE. ALL SITE CONDITIONS TO REMAIN AS-IS.
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2025 | COT - LCPL - Plumbing Intermediate | Passed | 4-28-25, plumbing intermediate approved. | |
| 05/01/2025 | COT - LCEL - Electrical Intermediate | Passed | 5-1-25, electrical intermediate inspection approved. Okay to install hard lids at progress areas. | |
| 05/01/2025 | COT - LCEL - Grounding/Bonding | Passed | 5-1-25, grounding/bonding approved. | |
| 05/01/2025 | BULD - Electrical Clearance | Passed | 5-1-25, panels are okay to be energized. INCR clearance sent to TEP. | |
| 05/01/2025 | COT - LCME - Mechanical Intermediate | Passed | 5-1-25, mechanical above ceiling approved. Okay to continue with installation of hard lids. | |
| 10/10/2025 | COT - LCBU - Framing | Passed | ||
| 10/10/2025 | COT - LCPL - Rough Soil | Passed | ||
| 10/10/2025 | COT - LCBU - Building Final | Passed | ||
| 10/10/2025 | COT - LCEL - Electrical Final | Passed | ||
| 10/10/2025 | COT - LCME - Mechanical Final | Passed | ||
| 10/10/2025 | COT - LCPL - Plumbing Final | Passed | ||
| 10/10/2025 | ENGR Engineering Final | Passed | Site is clear. | |
| 10/10/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 10/10/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 11/12/2025 | COT - FCON - Fire - Final | Passed |