Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
11/08/2024
Applicant:
Jeff Cooper
Description:
Remodel existing guest rooms

Permit Reviews

Permit Number - TC-COM-1124-02153
Permit Status: Issued
Permit Description: Remodel existing guest rooms
Start Date Submittal Complete Date Status  
04/08/2025 COMMERCIAL REVIEW - FULL REVISION v.1 04/29/2025 REQUIRES RESUBMIT Review Details
05/01/2025 COMMERCIAL REVIEW - FULL REVISION v.2 05/19/2025 APPROVED Review Details
01/15/2025 RESTAMP - COMMERCIAL v.1 01/16/2025 APPROVED Review Details
09/22/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 09/22/2025 APPROVED Review Details
01/06/2025 COMMERCIAL REVIEW - FULL v.2 01/15/2025 APPROVED Review Details
05/19/2025 RESTAMP - COMMERCIAL v.1 05/22/2025 APPROVED Review Details
11/12/2024 COMMERCIAL REVIEW - FULL v.1 12/10/2024 REQUIRES RESUBMIT Review Details
06/20/2025 COMMERCIAL REVIEW - FULL REVISION v.1 07/02/2025 APPROVED Review Details
09/18/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/22/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-1124-02153
Permit Status: Issued
Permit Description: Remodel existing guest rooms
Date Description Comments
11/12/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
04/04/2025 Project Description: Record P25WX00224: Sewer Connection Permit Record Status: Final MARRIOTT STAR PASS HOTEL - GUEST ROOM T.I.'S: D1 PER PLUMBING DRAWING P1.0 K1 PER PLUMBING DRAWING P1.1 CD2 PER PLUMBING DRAWING P1.2 CD2 ALTERNATE PER PLUMBING DRAWING P1.3 CK2 PER PLUMBING DRAWING P1.4 K2 PER PLUMBING DRAWING P1.5 CONNECTING TO EXISTING BUILDING SEWER PER DRAWINGS AND HISTORIC SEWER PERMITS #PT03S02681 DATED 5/30/03 AND #PT03S05878 DATED 3/15/04 CONNECTING TO EXISTING 7- 2" WATER METERS PER PIMA MAPS AND HISTORIC SEWER PERMITS #PT03S02681 DATED 5/30/03 AND #PT03S05878 DATED 3/15/04
01/15/2025 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-1124-02153
Permite Description: Remodel existing guest rooms
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
07/18/2025 COT - HCEL - Electrical Above Ceiling N/A Canceled
09/12/2025 COT - FCON - Alarm - Final N/A Partial Pass Fire alarm shall be cleared of all deficiencies.
10/22/2025 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass Level #3, room units 3100 - 3114, 3114 - 3234. Ok to cover bathroom ceilings in progress areas.
10/08/2025 COT - HCEL - Electrical Final N/A Partial Pass 10/8/25: TCO Level 4 for units 7215,7216,7217,7218,7219,7220,7221,7222,7223,7224,7225,7226,7227,7228,7229,7230,7231,7232,7233,7234.
09/16/2025 COT - FCON - Fire - Final N/A Partial Pass Ok for tco level 4 for buildings 4,5,and 6.
09/12/2025 COT - HCPL - Plumbing Final N/A Partial Pass Building #7; Level #5, Rooms 5725 - 5748: complete. Ok to apply for TCO for level #5.
09/16/2025 COT - HCBU - Building Final N/A Partial Pass Level #4, Building #7 complete. Ok to apply for level #4 TCO.
06/23/2025 COT - HCPL - Plumbing Intermediate N/A Re-inspection required Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025
6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor.
06/23/2025 COT - HCEL - Electrical Intermediate N/A Re-inspection required Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025
6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor.

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-1124-02153
Permit Description: Remodel existing guest rooms
Total Completed Inspections - 2
Date Description Inspector Results Comments
09/10/2025 ENGR Engineering Final Passed
09/09/2025 TRSP - ROW - Final/Close-Out Passed

Documents

File Name Document Type  
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
25I0520_1 TURNERRES 09 19 2025 1707-2025-09-22_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-3810.3 STARR PASS GUESTROOM OWNER REVISION 2_V1.PDF DOCUMENTS VIEW
STANTEC PERMIT REVISION 2 (GUESTROOMS) 2025-05-29_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-3810.3 STARR PASS GUESTROOMS DELTA3_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-3810.3 STARR PASS GUESTROOM PERMIT SET DELTA 1 AND 2_V2.PDF DOCUMENTS VIEW