Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCPL - Plumbing Intermediate
Permit Number - TC-COM-1124-02153
Inspection Description - COT - HCPL - Plumbing Intermediate
Inspection Status - Re-inspection required
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/23/2025 | COT - HCPL - Plumbing Intermediate | Re-inspection required | Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025 6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor. |
|
| 07/07/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025 6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor. 7/7/25: 6th floor shower pan under water test ok to proceed with tile placement at progress areas. |
|
| 07/15/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 7/17/25: plumbing intermediate approved in units (5725,5726,5727,5728,5729,5730,5731,5732,5733,5734,5735,5736,5737,5738,5739,5740,5741,5742,5743,5744,5745,5746,5747,5748 | |
| 07/21/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025 6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor. 7/7/25: 6th floor shower pan under water test ok to proceed with tile placement at progress areas. 7/17/25: plumbing intermediate approved in units (5725,5726,5727,5728,5729,5730,5731,5732,5733,5734,5735,5736,5737,5738,5739,5740,5741,5742,5743,5744,5745,5746,5747,5748 7/21/25: plumbing intermediate approved in units 4726,4728,4730,4732,4734,4636,4738,4740 |
|
| 07/25/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025 6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor. 7/7/25: 6th floor shower pan under water test ok to proceed with tile placement at progress areas. 7/17/25: plumbing intermediate approved in units (5725,5726,5727,5728,5729,5730,5731,5732,5733,5734,5735,5736,5737,5738,5739,5740,5741,5742,5743,5744,5745,5746,5747,5748 7/21/25: plumbing intermediate approved in units 4726,4728,4730,4732,4734,4636,4738,4740 7/25/25: plumbing intermediate approved in units 4725,4727,4729,4731,4733,4735,4737,4739,4741. |
|
| 08/05/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 8/5/25: Showers under test in units 4725,4727,4729,4731,4733,4735,4737,4739,4741.4726,4728,4730,4732,4734,4636,4738,4740 | |
| 08/19/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 8/19/25: plumbing in wall approved in restrooms for units 7233,7231,7229,7227,7225,7223,7221,7219,7216,7215,7217,7218,7220, 7222,7224,7226,7228,7230,7232,7234 | |
| 08/26/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Building #2; Level #6, rooms 6215 - 6234; Building #1 Level #6, rooms 6105 - 6106, 6109 - 6114. | |
| 09/02/2025 | COT - HCPL - Plumbing Intermediate | Canceled | Contractor cancelled; reschedule for 4,September. | |
| 09/17/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Bathroom in wall plumbing at Building #2; Level #4: Rooms 4214 - 4236; Building #1; Level #4, Rooms: 4101 - 4107, 4109 - 4113. | |
| 10/14/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 10-14-25: verified supports on pex lines in room's, 5101, 6106, 6107, 4101. Also verified the following showers under test in Building 2-room's 4103-4114, 4212-4224. Okay to continue with construction at progress areas. | |
| 12/03/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 12/3/2025 partial pass. Bathroom only 7th floor approved. Okay to proceed progress areas. |