Inspection Status: Re-inspection required

Inspection History: COT - HCPL - Plumbing Intermediate 

Permit Number - TC-COM-1124-02153

Inspection Description - COT - HCPL - Plumbing Intermediate 

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
06/23/2025 COT - HCPL - Plumbing Intermediate  Re-inspection required Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025
6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor.
07/07/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025
6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor.
7/7/25: 6th floor shower pan under water test ok to proceed with tile placement at progress areas.
07/15/2025 COT - HCPL - Plumbing Intermediate  Partial Pass 7/17/25: plumbing intermediate approved in units (5725,5726,5727,5728,5729,5730,5731,5732,5733,5734,5735,5736,5737,5738,5739,5740,5741,5742,5743,5744,5745,5746,5747,5748
07/21/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025
6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor.
7/7/25: 6th floor shower pan under water test ok to proceed with tile placement at progress areas.
7/17/25: plumbing intermediate approved in units (5725,5726,5727,5728,5729,5730,5731,5732,5733,5734,5735,5736,5737,5738,5739,5740,5741,5742,5743,5744,5745,5746,5747,5748
7/21/25: plumbing intermediate approved in units 4726,4728,4730,4732,4734,4636,4738,4740
07/25/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Partial pass. Rough in electrical in walls. 6th floor 24 units east end for guest rooms pending puddy pack on all receptacles at party walls within 2’ from each other. 6/11/2025
6/23/25: 6725-6748, 6742 not ready, 6746 not ready, 6743 not ready, 6750 not ready, 6741 not ready, 6739 not ready, supports on pex lines required throughout top track and vertical/horizontal runs, incomplete rough-ins throughout. Full walk through required on next inspection. Copper hangers must be coated or taped off. Putty packs required at bathroom receptacle that are in back to back cell within 24" seal penetrations in floor.
7/7/25: 6th floor shower pan under water test ok to proceed with tile placement at progress areas.
7/17/25: plumbing intermediate approved in units (5725,5726,5727,5728,5729,5730,5731,5732,5733,5734,5735,5736,5737,5738,5739,5740,5741,5742,5743,5744,5745,5746,5747,5748
7/21/25: plumbing intermediate approved in units 4726,4728,4730,4732,4734,4636,4738,4740
7/25/25: plumbing intermediate approved in units 4725,4727,4729,4731,4733,4735,4737,4739,4741.
08/05/2025 COT - HCPL - Plumbing Intermediate  Partial Pass 8/5/25: Showers under test in units 4725,4727,4729,4731,4733,4735,4737,4739,4741.4726,4728,4730,4732,4734,4636,4738,4740
08/19/2025 COT - HCPL - Plumbing Intermediate  Partial Pass 8/19/25: plumbing in wall approved in restrooms for units 7233,7231,7229,7227,7225,7223,7221,7219,7216,7215,7217,7218,7220, 7222,7224,7226,7228,7230,7232,7234
08/26/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Building #2; Level #6, rooms 6215 - 6234; Building #1 Level #6, rooms 6105 - 6106, 6109 - 6114.
09/02/2025 COT - HCPL - Plumbing Intermediate  Canceled Contractor cancelled; reschedule for 4,September.
09/17/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Bathroom in wall plumbing at Building #2; Level #4: Rooms 4214 - 4236; Building #1; Level #4, Rooms: 4101 - 4107, 4109 - 4113.
10/14/2025 COT - HCPL - Plumbing Intermediate  Partial Pass 10-14-25: verified supports on pex lines in room's, 5101, 6106, 6107, 4101. Also verified the following showers under test in Building 2-room's 4103-4114, 4212-4224. Okay to continue with construction at progress areas.
12/03/2025 COT - HCPL - Plumbing Intermediate  Partial Pass 12/3/2025 partial pass. Bathroom only 7th floor approved. Okay to proceed progress areas.